Beyond rounding up the usual suspects:
Towards effective quality management policies for
production ramp-ups in high-tech supply chains
Henk Akkermans
ha@uvt.nl
Tilburg University
Economics and Business Administration,
Dept. of Information Systems and Management
PO Box 90153, 5000 LE Tilburg, The Netherlands
Abstract
This study investigates the issue of managing quality during production ramp-ups
in high-tech supply chains. It combines an in-depth case study of one particular
high-tech supply chain setting with insights from the recently-emerging literature
on behavioral operations and synthesizes these two into a system dynamics
simulation model.
Model analysis suggests that isolated and intuitively appealing quality
management policies are likely to lead to suboptimal or even detrimental results.
Of crucial importance is finding the balance between ramping up production rates
sufficiently fast to capture short-lived market demand and avoiding to increasing
production starts so high that workload levels in the supply chain move beyond the
tipping point. This means that when workloads become too high, the entire supply
chain can get bogged down in a vicious cycle of high workloads leading to low
quality levels, which lead to high rework levels and hence to even higher
workloads.
Especially promising policies to be used in combination are, firstly,
moderate production ramp-up rates that turn out to generate more timely output
than overly aggressive production ramp-ups. Secondly, policies that leverage the
expertise that can be gained from analyzing defective units that cannot be repaired
easily downstream, as these may yield especially valuable knowledge regarding
hidden quality issues in upstream manufacturing operations. Other measures such
as installing quality gates or superior error detection equipment are found to be
ineffective or even detrimental for improving supply chain performance.
1. Introduction
In today’s “high-clockspeed” industries (Fine 1998), such as the electronics industry,
ever-shrinking product-life cycles lead tot the need for ever-shorter production ramp-
ups. The shorter and steeper the production ramp-up, the greater the opportunity to
capture the short-lived market demand while it is still there. The earlier your product
is on the market, the less it will suffer from price erosion. Because of these short-life
cycles, neither product designs nor manufacturing methods and tools are typically
fully developed when the first production runs start. One thing is worse than not
having your product out there early: having a defective product out early. Therefore,
effective quality management during production ramp-up has become of paramount
importance.
The current omnipresence of decentralized supply chains has complicated this
challenge of quality management during ramp up further. This is not just because
different stages of production may now take place on different continents, or at least
in different companies. Decentralized supply chains also pose a specific challenge for
quality management, which is the following. Typically, in high-tech electronics
assembly, quite some of the errors that are generated upstream in the supply chain can
only be fully detected downstream. This has two main reasons. Firstly, upstream one
can only test the components, but further down the production process these
components can be damaged during handling or transport, for instance when other
components are added to the semi-finished product. Secondly, and this is most
important, many of the errors that are generated upstream can only be detected when
the product is fully assembled, as they only become visible through the interaction of
the components with one another. And this makes it inherently impossible to detect
such errors upstream. So, errors that are generated upstream can only be found
downstream, but then the root cause of these errors has to be traced back to upstream
operations. Obviously, in a fast-moving industry, such communication and joint
problem-solving can be very problematic indeed.
Unfortunately, there is very little sound and well-tested guidance on how to
proceed in this matter. There is a well-developed literature on quality management
during product development processes, and in particular in IT system design, but it is
unclear how this might translate into prescriptions for production during ramp-up. On
the other hand, there is a wealth of practitioner literature on quality management in
production, especially from the quality management/TQM/Kaizen/lean manufacturing
movement, but here the implicit assumption is almost always a steady-state of
production rates, whereas during production ramp-up there is never such a steady
state.
So, what do companies do? Typically, as Captain Renault originally ordered
his policemen to do in the movie classic Casablanca, they order to “round up the usual
suspects” on the basis of common sense, implement such policies as well as they can
and hope for the best. Of course, this leaves much to be desired. It is usually unclear
to management who of these usual suspects are really guilty, e.g., what measures will
work best and where and when. It is certainly not clear to what extent they reinforce
each other or if they may even reduce each other’s effectiveness. Unlike the infamous
Captain, management does not go for the obvious measures because they don’t care
what the outcome will be, but rather because they cannot resort to a body of theory
that goes beyond these obvious candidate measures.
This paper describes a study that employs simulation analysis to explore the
beginnings of such a theory, to start moving beyond “rounding up the usual suspects”.
This study introduces and analyses a simulation model of production ramp-up in a
high-tech supply chain on the basis of a field study in 1995 of a personal computer
manufacturing company with a two-stage internal supply chain and external
component suppliers. In this original field study, it appeared that what management
wanted to do to improve quality during production-ramp up was often not effective.
The present study takes this original setting as a start, but employs a simplified
rendering of the more detailed simulation model that was developed in 1995 to guide
the analysis back then. It finds that, with the present model, the fundamental efficacy
issues with many of the obvious candidate policy measures persist.
This study presents policy analyses with the simulation model of different
quality improvement measures. Some of these turn out to be effective, others turn out
to have marginal effects or even downright negative effects on quality. Some of these
outcomes are in line with managerial common sense. Most of them are not.
A first policy experiment was to explore the benefits of a less steep ramp-up
production scenario. This was declared out of bounds by management from the start,
given the marketing considerations sketched before. However, what management did
not expect was that a less aggressive ramp-up scenario would lead to more product
being available on the market sooner, rather than later.
A policy experiment whose outcomes did fit with managerial intuition was
that high component quality would have a beneficial effect on both quantity and
quality of factory output. What management also did expect was that the ability to
maintain consistently high quality in upstream or downstream manufacturing
operations would be beneficial. What management could not foresee was that
consistently high upstream manufacturing quality yielded only marginal
improvements in the analysis, whereas consistently high downstream manufacturing
quality would lead to excellent results.
Another scenario that showed only marginal improvements was to install
equipment with superior error detection quality. This was all the more frustrating
since management was considering making such investments at the time. Significant
contributions were expected by management from improving the quality and quantity
from feedback from downstream repair work to upstream manufacturing. These were
confirmed and could be implemented against significantly lower cost.
One policy that sounded especially attractive to management was the notion of
a quality gate or stage gate. In the context of manufacturing, this meant that units
could not move on to downstream production until a certain quality level had been
reached in upstream production. Policy analysis suggested that setting a high quality
gate would have disastrous results on supply chain productivity and output. Setting a
modest quality gate might have some benefits.
Finally, this study looks at several combined policies, especially for those
measures that would not require major restructurings in operations. Here a
combination of a less aggressive ramp-up target in combination with better feedback
from and more resources in downstream repair work appears especially promising.
In the concluding parts of this paper, the proposition is put forward that what
management may really need is not a list of setting-independent usual suspects for
improvement, but a deeper understanding of what really drives quality during
production ram-up. Here a link is made to existing theories from behavioral
psychology and operations management that focus on the important feedback effects
between schedule pressures, workload and error rates. The higher the schedule
pressure, the higher the workload (Oliva and Sterman 2001, Akkermans and Vos
2003). When workloads pass a certain threshold, process quality will drop so error
rates will rise (an insight from psychology that goes back to Yerkes & Dobson 1908).
This leads to more rework, which further increases workload and limits output so that
schedule pressure increases as well. An effective quality management policy during
ramp-up ensures that the supply chain does not get trapped into such vicious cycles of
every-greater workload and ever-lower quality and output rates.
2. Literature review
2.1. Production-ramp up as a “missing link”
There is relatively little academic literature that deals specifically with the issue of
quality management during production ramp-ups and this is quite understandable.
After all, also in practice production ramp-ups form something of a “missing link”
between product-development and volume production. This is an area that is not well
understood and that often leads to major problems in timely and cost-effective market
introductions. (c.f. Mass & Berkson 1995, Akkermans 2001). So it should come as no
surprise that there is no adequate body of theory to fall back upon either.
Why is quality management such an issue during production-ramp up in high-
tech supply chains? Because quality is never at market standards when a product
design is released by product development into production. On the one hand, this is an
issue of industry clockspeed (Fine 1998). There is a rush to get to the market first and,
therefore, also a rush to get into production ASAP (Iansiti & MacCormack 1997). On
the other hand, design imperfections are inherent to the nature of high-tech products:
it is practically impossible to figure out precisely how a design will turn out in terms
of quality from the drawing board or CAD screen. For this, specific production
expertise is need and also a lot of testing, so, production, and not just of a single
prototype, but of actually some volumes.
What theory is then available? Definitely, the literature of the two functional
areas that production ramp-up falls in between: product development and volume
production. These are two strong and well-developed fields of expertise, both with
their well-established sets of ideas on how to manage quality. We will select some of
the key publications in these very broad fields to investigate what they have to say for
this area.
Given the dominance of product development and high-volume manufacutring
it is not surprising that most of the ideas that are tried out in practice by managers to
deal with production ramp-up issues stem from either one of these areas.
Unfortunately, these fields often contradict each other for production ramp-up
policies. For instance, Boehm & Turner (2005) note that one barrier to the
introduction of agile processes is the conflicts in development process that arise when
agile processes are merged with standard industrial processes. And, at any rate, as
Mass & Berkson noted in 1995, companies that use “the theme of the month” to get
process improvements in this area rarely see much benefit.
So, we need more. Here comes into play a third source of literature that can be
applied to this specific area. This is the relatively recent modeling literature on the
interplay between behavioral psychology and operations management elements in
how individuals and organizations deal with stress and market pressures. We will look
at this literature as well, also because the simulation model that is introduced in
Section 3 has some of the relationships suggested in this literature at its core.
Finally, there are some publications that deal specifically with the issue of
quality management during production ramp-up in supply chains, although their
insights are not easy to access, interpret and use in follow-up studies We will look at
those as well.
2.2. Insights from lean production
What we call today “lean” or “six-sigma” or “lean-six-sigma” was started in the
1970s in Japan, notably Toyota. A central element in this approach to production
management has always been quality, rather than quantity or speed (Ohno 1988,
p-107). These ideas regarding quality come from some U.S. quality experts some
decades earlier, notably Deming, Juran and Feigenbaum. The latter wrote down the
core concept back in 1961: “The theme...is ‘make them right the first time.’ Emphasis
is on defect prevention so that routine inspection will not be needed to as large an
extent.” (Feigenbaum 1961, quoted in Schonberger 1982, p.47.).
Originally, these ideas were targeted to improving ongoing production, not
production during ramp-up. That is not to say that the Total Quality Management
(TQM) concept or lean has not been applied to product development and production
ramp-up, see e.g. Kennedy 2003).
What doing-it-right the first-time means for a production line was vividly
described by Womack et al. in their study of Toyota assembly plants: “each worker
along the line can pull a cord just above the work station to stop the line if any
problem is found (...) but the line is almost never stopped, because problems are
solved in advance (..) (Womack et al. 1990, p.80). And yet, “we observed almost no
rework areas at all. (...) there were practically no buffers...and there were no parts
warehouses at all.” (p.80). So, very strict quality controls are assumed to lead to very
low reject levels and hence to very low inventory levels, which makes it again easier
to keep quality levels very high.
Lean manufacturing suggests a variety of techniques to achieve such
consistently high quality levels. Quality circles are among them and also so-called
“poka-yoke methods” or failsafe methods (c.f. Schonberger 1984, Hall 1987). The
first techniques certainly assumes that quality is not perfect, but that continuous
improvement is a natural state of affairs, the second one does assume that perfect
quality is attainable, simply because it is possible to develop tools that make the
occurance of error impossible. Both techniques, and most others, do assume a
development over time. But neither of them treat the issue of production ramp-up as
problematic in its own, which remains understandable from the roots of lean in the
textile and automotive industry, where product-life cycles are usually fairly long and
the production ramp-up period is small relative to the period of stable volume
production. Similar comments can be made about the Six Sigma practitioner
movement as well. This approach to lean, made famous by its adoption by GE, has as
one of its One of the chief problems that it is narrowly designed to fix an existing
process, not an inherently new setting (c.f. Morris 2006).
In summary: quality management is really fundamental to lean production
operations, but historically the phase of production ramp-up has not been the focus of
this literature. Its implicit assumption remains one of stable volume production, and
quality improvement recommendations that fit an environment where design and
operations quality are fairly high already. Managers who apply recommendations
from the lean practitioner literature to production ramp-ups settings too lightheartedly
will do so at their own peril.
2.3. Insights from agile product development
In research in product development, software product development is an important
area of attention, for several reasons. However, management insights gained in the
development of software tend to find their way into other, less extremely innovation-
driven industries, for instance the car industry (Ward et al. 1995, Iansiti &
McKormack 1997)
In software development, the issue of how to get to high levels of quality fast,
very fast, has long been a crucial managerial concern, given the high degrees of
innovation and shot life cycles of many software applications. Broadly speaking, there
are two generic kinds of development models: sequential or waterfall models and
what Molokken-Ostvold & Jorgensen (2005) call “flexible” development models.
- Waterfall models represent the “classical” (c.f. Brooke 1979) mode of software
development. This means sequential processing of the generic phases: analysis,
design, programming, testing. These are most suitable when technology, product
features, and competitive conditions are predictable or evolve slowly [20].
- Flexible development models can be “incremental”, “evolutionary” or “agile”, but
the bottom-line is always that several parts of the system are being developed in
parallel, in small increments, and in close cooperation and with close
communication between client and developers (Molokken-Ostvold & Jorgensen
2005). Interestingly, this is also where “lean” product development models should
be located. Here one talks about set-based concurrent engineering, with many
concepts being developed concurrently for each subsystem, that are evaluated
against each other, so that the weak concepts can be eliminated, and insights from
each other them can be combined in different ways in the final product (Kennedy
2003, p.122).
This distinction in product development is certainly not specific to software. In
1984, Takeuchi & Nonaka (1984) described these two different concepts of “the
product development game” as the difference between playing a relay race or rugby
on the basis of their work with high-tech electronics and automotive companies such
as Fuji, Cano and Honda.
An important concept in product development is the notion of the stage-gate. A
stage-gate model describes a work process from idea to delivered product. The model
presents the stages of product development in a generic abstract project life cycle
suitable for high-level management. Two stages are connected through a gate, and at
every gate management can decide to stop the project or move to the next stage. This
is at the managerial level. Importantly, such stage-gates can be applied in both types
of development models, but with a crucial underlying difference, as Karlstrém &
Runeson (2005) note. They state that at the level below the managerial decision-
making process, at the technical level such a stage-gate model can relate to a waterfall
development process or an agile development process. In the waterfall model,
functionality is fixed: the project cannot move to the next stage until a certain level of
completeness and quality has been reached here. So, time becomes flexible, and this is
why waterfall models are especially associated with large project schedule overruns.
In agile methods, time is fixed (“‘time-boxing” as it is also called). So, functionality
and quality become variable.
In summary, the field of agile product development contains numerous
suggestions on how quality improvement can be speeded up in a volatile setting.
Parallel execution of tasks, intensive communication and feedback between stages are
among the most directly relevant ones. However, we should not forget that in
production ramp-ups, we ware NOT talking about designs, but about actual units of
product. And when these units are defective, they cost money when they are not
shipped to the customer and may cost even more money when they are shipped.
Again, managers who apply recommendations from the agile product development
literature to production ramp-ups settings too lightheartedly will do so at their own
peril.
2.4. Insights from “behavioral operations”
Quality management during production ramp-up is clearly a complex phenomenon,
with multiple interactions between different production stages, and multiple
interactions between human behavior and cognition and the operations they influence.
Although this phenomenon itself has not been investigated extensively from this
perspective, there is a nascent literature that acknowledge this inherent complexity
and takes both behavioral and operational considerations into account. Gino & Pisano
(2006) label this emerging body of research as “behavioral operations”, and they
define it as “the study of attributes of human behavior and cognition that impact the
design, management, and improvement of operating systems, and of the interaction
between such attributes and operating systems and processes” (Gino & Pisano 2006,
p.9.). Earlier on, Boudreau at al. (2003) also suggest a research agenda for the
interface between operations management and human resource management, as
“human responses to OM systems often explain variations and anomalies that would
otherwise be treated as randomness or error variance in traditional operations research
models”.
In the context of the present article, what are important findings from this work
in behavioral operations? Interestingly, of these use system dynamics methods and
models, just like the present study, and most if not all of them trace back to John
Sterman’s seminal publication in weaving together operations and behavior from a
dynamics perspective on how management decisions are made in the Beer Game
(Sterman 1989). From this population, different studies present different key
messages. Within the context of the present study, the following ones appear most
relevant:
1. Rising workloads lead to more errors. Firstly, there is the notion that when
workloads rise beyond a certain level, productivity will drops and error rates will
increase. This finding has a long history in cognitive psychology, and goes back to
neuropsychological research from the beginning of the 20" century (Yerkes &
Dodson 1908). “This Yerkes—Dodson curve—originally derived from experiments
testing how rats running through a maze responded to electric shocks of varying
size—depicts a curvilinear relationship between stress and performance. Initially,
stress improves performance, but, as it continues to increase, performance eventually
declines”. (Repenning 2003, p.312). This “law for all seasons” (Eigen 1994) has
found several applications in system dynamics oriented research in behavioral
operations. For instance, Rudoph & Repenning (2002) show how this “law” can
explain the dynamics of disasters such as plane crashes and their organizational
equivalents. Akkermans & Vos (2003) use this notion to explain why sales campaigns
can have disastrous effects on the service supply chain when too many orders are
pushed downstream.
2. Higher schedule pressure leads to more errors. One special manifestation of
this relation between workload and error rate is that it is not really just the amount of
work one has on one’s plate, but also the awareness of how much really should be
done to get back in line with the company target for output. This negative effect of
schedule pressure on the error rate has been empirically established by Oliva &
Sterman (2001) in the service industry and found in the context of product
development in high-tech electronics by Mass & Berkson (1995).
3. Work pressure reduces detection rates. One other indirect consequence of the
Yerkes-Dobson law is that increasing work pressure leads to lower levels of error
detection. One reason why is 1“ order and obvious: if you are too busy, errors slip
through. Ford & Sterman (2003) also point at another, more 2" order effect: a
collective urge amongst project mangers to hide rework that they know will have to
be done sooner and later in order not to be the bringer of bad news. Hence,
management forms a collective “Liars club”, as Ford and Sterman put it.
4. Error prevention is less rewarding than error solving. This is also one of the
reasons why a fire-fighting culture is so persistent in product development and
production settings. As Repenning & Sterman (2001) point out, “nobody gets credit
for solving problems that never happened.” So, companies will have a persistent
preference for investing in becoming better in problem solving than in error-
prevention.
5. Errors and workloads cascade down in multi-stage processes. This
particular finding is all the more detrimental for performance in a multi-stage setting
such a supply chain because both errors and workloads will tend to cascade down in
them. For instance, Repenning et al. (2001) found that persistent firefighting in NPD
resulted from a positive feedback process whereby lack of attention to the early
phases of the development process results in serious problems when projects reach
their downstream phases. Those problems, in turn, consume scarce engineering
resources that would otherwise be dedicated to the early stages of the next generation
of products.
Ford & Sterman (1998) showed this in an earlier study of the dynamics of the
product development process. They emphasized that, in product development,
changes inherited by downstream phases from upstream phases corrupt downstream
work, which must then be corrected. When inherited changes are discovered by a
downstream phase they are returned for correction or improvement to the phase where
the change was generated. Akkermans & Vos (2003) analyzed how this can lead to a
cascading of workload and errors in a service supply chain. In a service supply chain
context, this cascading of workloads was also investigated by Anderson & Morrice
(2001) and Anderson et al. (2005).
6. Effective (downstream) repairs lead to more (upstream) expertise. The
notion of the learning curve is well established in operations management and on
example of a behavioral phenomenon that has become part and parcel of OM theory
and practice. What the behavioral operations literature adds to this is specific notions
of how and where people learn from operations and where and how this knowledge is
best applied. Oliva & Sterman (2001) show how service staff increases its
productivity through learning by doing in service encounters. In the context of
processing legal cases, Akkermans & van Oorschot (2005) modeled how experienced
staff would become more adept in accessing cases upstream in their service supply
chain so that their subsequent processing might become easier.
2.5. Examples of an integrated behavioral operations approach to
production ramp-ups
There are some examples of just the type of study that is presented in this article. Two
of them are consulting cases. Mass & Berkson (1995) describe insights from what in
fact was the precursor to the original field study that forms the basis for the current
research. Their work is focused on managerial insights regarding the unintended side
effects of setting overly aggressive commercialization targets for product
development projects in high-tech electronics. Several of their findings will indeed
resonate back in the current study. However, the model they base their findings upon
is not in the public domain. Akkermans (2001) describes qualitative insights from a
study in the high-tech electronics sector on issues related to premature release of
designs into production driven by strong schedule pressures. Again, there is no
description of the model employed here available, although the insights are in line
with what the current study finds.
Anderson & Joglekar (1996) wrote a conference paper with a promising title
on modeling the dynamics of technological ramp-ups, but this really focuses on the
relation between process innovation and product innovation, not on quality
management issues. Perhaps the most promising of all is Juergen & Milling (2006),
albeit that this is presently only a conference paper without model documentation.
This paper describes insights from production ramp-ups in the automotive sector,
where the authors find that there is a trade-off between starting production early on, to
maximize learning and early feedback into design, and waiting until production
designs have accomplished a certain level of series production readiness. In the future,
this paper may shed light on how effective production ramp-up policies may be
different in a medium industry clockspeed setting such as the automotive sector.
3. Research approach and environment
This study is very much anchored in the real world. Its origins lie with a consulting
study conducted by the author in 1995 for a major U.S. high-tech electronics firm. For
the present article, a new and simplified simulation model of the field setting that was
encountered there has been developed without losing the essential characteristics of
the model. In this section, we first explain the research methodology. Then we
introduce the empirical supply chain setting, the original management concerns and
explain how the original field study was conducted. This section concludes with a
brief explanation of the modeling and analysis that has taken place 11 years later, for
the research that is presented in the current paper.
3.1. Research approach: Synthesizing research site findings with
behavioral operations theory in a simulation model
In its methodology, the research reported in this article is similar to published work by
Akkermans & Vos (2003) in Production and Operations Management and by Holweg
et. al. (2005) in the Journal of Operations Management. Partly, because in all three
papers a system dynamics model is presented that is based on a synthesis of field
work, in the case of Akkermans & Vos a consulting study from the telecom industry,
in the case of Holweg et al., an automotive research project sponsored by industry,
and in the case of the current paper a consulting project with a high-tech electronics
company.
Another source of similarity is that in all three papers this field work is used as
input for follow-up analysis and synthesis, which generates a simulation model and
insights that go beyond the findings from the original field studies. A final aspect of
similarity is that the simulation model that is presented here was elicited through the
use of causal loop diagrams and process mapping (Evans 1998, Sterman 2000).
One notable difference with these two earlier articles is that the present study
deals with less “tangible” issues than amplification effects in a telecom service supply
chain or the physical automotive supply chain and scheduling policies. As a result, the
present paper needs to make a better case for its assertion that the “soft” causal links
that were derived through group knowledge elicitation (Vennix 1996) in its field study
are plausible and valid ones. Back in 1995, this would have been very difficult.
Fortunately, the last decade has seen a number of publications that address similar
issues, which we have labeled in the previous section as “behavioral operations”.
3.2. The research site
The client company in this case study was a major U.S. electronics manufacturer that
had been very successful, enjoying considerable increases in market share in a market
that was strongly growing. In the 5 years prior to this field study, its revenues growth
was about 40%/year. The quality image of most of its products was also above
industry average. Like all other firms in this industry, it was faced with shortening
product life cycles, price pressure, very steep production ramp-up curves and a never-
ending need to add new technological improvements to subsequent designs. On top of
this, success was taking its toll as well. As a result of this fast growth, there were
many problems with meeting delivery dates, getting adequate levels of quality and
coordinating the mushroomed set of production units, systems and processes.
Prior to the field study the current research focuses on, the late Nathaniel Mass,
then working with McKinsey & Co., had conducted two system dynamics modeling
projects for this company to meet these growth challenges. Selected insights from
both have become available in the public domain. One focused on the external supply
chain with distribution channels. This case was written up by John Sterman in
Sterman (2000), p. 743-755. The other study focused on product development issues
and selected insights from this case were published in Mass & Berkson (1995).
Both studies had been extremely successful, and it was only natural that the area
in between the two business domains covered so far would be investigated in a similar
manner: the dynamics of the internal production supply chain itself. Together with
Nat Mass, the author of the current paper conducted this system dynamics modeling
study. In order to keep up with the tremendous demands that its highly dynamic
industry in combination with the company’s fast growth placed on production quality,
management was had put extensive quality assurance measures in place and was
considering additional ones. In order to evaluate the effectiveness of the existing
measures and the proposed additions, company management commissioned an
exploratory system dynamics study that would focus on its production supply chain
for personal computers (PCs), which is visualized in Figure 1.
LEGEND
L = Mfg/rework stage
< = Test stage
[> = Transportation stage
VY = WLP.) inventory
Figure 1: Schematic overview of process stages in the actual supply chain
Broadly speaking, this supply chain consisted of two main stages.
- In the first stage, “upstream manufacturing”, a semi-finished product was created,
a Printed Circuit Board (PCB) with mounted inter which was tested in two
separate test stations, one for the Integrated Circuits or ICs themselves and the
other for the functions they should collectively perform. Products that failed these
tests would be repaired and fed back into the production stream
- Inthe second stage, “downstream manufacturing”, which could be on a
production line next door or on the other side of the globe, additional components
were added to this semi-finished product in two main steps, interceded with
various tests and audits, leading to three types of rework for defective units. Of
particular concern is the rework process stage called internally “the Pit”, because
this is the place where all the defective units that could not be repaired
immediately would pile up.
3.3. Management concerns in the field study
At the time, company management had already set in motion plans for improving
quality during production ramp-up and was considering to set up more. However, it
could only select these on basis of common sense. It could only “round up the usual
suspects” and hope that the really effective ones were among those. Since it felt
uncomfortable about this and had already experienced spectacular success with
developing simulation models of its product development processes, it commissioned
a study to investigate the effectiveness of different quality improvement measures.
Table 1 summarizes managerial thinking in this area at the time. To some of the
measures that were being considered management was fairly skeptical, to some
simply opposed. An example of the former is the idea of putting experienced staff into
the Pit rework area to generate production insights from their repair work on defective
downstream units. At the time, nobody really knew for certain what that might give in
production. An example of the latter is a less steep production ramp-up schedule.
Even discussing this was fairly controversial at the company, since its success so far
had been based on its ability to move faster than others in very fast-moving markets.
Quality Measure under
consideration at the time
Ex ante managerial
inclination
Ex ante underlying reasoning
Schedule less steep
production ramp-up
Ensure high component
quality
Introduce fail-safe
equipment and
production methods
Install superior error
detection equipment
Increase pit repair work
staff numbers and skill
levels
Set up a quality gate
before downstream
production
Not to be pursued,
unacceptable for Marketing
Pursue, but may be difficult
to implement
Positive, but very difficult to
implement so more
something for the long term
Definitely pursue
Pursue possibly, or forget
about pit stock, which is best
Pursue, but unsure about
location and level
Cannot allow delays in getting product to
the market
Better quality in means better quality out
Doing-it-right-the-first time
No defective materials should be allowed
to move downstream
On the one hand: repairing these unit
i sights into upstream quality 2
's job that requires very
skilled staff, who we can’t really afford to
miss elsewhere
No defective materials should be allowed
to move downstream
may
Table 1: Quality measures under consideration with management in field setting
Other measures simply seemed sensible ideas, were really “the usual suspects” for
any company that wants to work on improving its product quality. Fail-safe
equipment, high component quality, superior error detection tools and quality gates all
fall in this category. Today, one would call these measures part of the toolbox of
“Jean” manufacturing. Then, the label was “world class” or Total Quality
Management or TQM, but the underlying reasoning was the same: no defective
materials should go into the supply chain, and when defects would occur they should
immediately be detected and corrected, not passed on further downstream.
3.4. Data collection and analysis at the research site
Data collection at the research site was conducted “from the ground up” (Glaser &
Strauss 1967, Miles & Huberman 1984), and through a variety of techniques. First, a
half-day brainstorm session was conducted by Nat Mass and the author with a small
number of key experts and managers in the company. In this so-called Group Model-
Building (Vennix 1996) brainstorm, the question was addressed: “When something
goes wrong in production, why is that and what happens as a result?” This discussion
was captured in causal loop diagrams (CLDs), in which the cause-and-effect relations
of the relevant variables were visualized, as well as the feedback loops connecting
them. Causal loop diagramming is a common tool utilized in system dynamics
modeling to define flows, feedback loops and system structures (c.f. Vennix 1996,
Sterman 2000). Causal maps are also used to synthesize findings in qualitative
research (c.f. Miles & Huberman 1984). In this session, a number of key causal
relationships were identified between outgoing product quality and various other
characteristics of the production system, such as work pressure, operator skills, design
fails or inspection quality.
On the basis of the results from this brainstorm session, the author developed —
in interaction with company staff, Nat Mass and other consultants — a
comprehensive system dynamics model of the various interactions in production
operations. Key data were collected to parameterize and calibrate the simulation
model. Then, a broad range of quality management measures was simulated to
evaluate their effectiveness on a stand-alone basis and in combination. All this was
done in a period of almost two months. The results of these experiments were
presented in a second workshop for the same group.
The reception of the outcomes was not positive. As the scenario analysis in
Section 5 will illustrate, managerial intuition was contradicted in many instances by
the policy analyses. In fact, the messages that came out were so contradicted that the
entire modeling study was dismissed on the grounds of incorrect formulation and
technical errors in the model. Certainly, no immediate implementation of its
recommendations was planned. And so, this author was left with the question: was the
model just “wrong” or was the way it was presented not successful in convincing
company management of the validity of its results?
3.5. Modeling and analysis one decade later
Over the course of the ten years that followed, there gradually became available
studies that presented similar findings as the controversial outcomes of this original
field study. These have been discussed in Section 2. This fed this author’s belief that,
although the relationships that had been developed “from the ground up” (Strauss ref)
with a small group of company representatives from one company in one moment in
time were actually fairly generalizable to a broader range of settings.
I therefore developed a new model, based upon the original detailed simulation
model, but this time stripped from parts that seemed unlikely to be changing its
overall behavior (e.g., not two subsequent test units but just one combined unit, no
separate audit rework site). I also made sure that the behavioral relationships
contained in this model were consistent with the model formulations regarding the
same relationships that had become available in the academic literature since then.
I compared the dynamic behavior of the new model broadly consistent with the
original one, certainly in its management implications. I also conducted the “usual”
test and experiments to assess the sensitivity of model behavior to changes in its key
assumptions. I then revisited the original managerial issues, the “ususal suspects” that
had been rounded up more than one decade earlier on, and used to model to
investigate their “guilt” for this more generic model. The main findings of this
modeling and analysis are presented in the subsequent sections.
4. Simulating production ramp-up dynamics in a high-tech
supply chain
In this section, we present a formal model that integrates the characteristics of the
dynamics of quality management during production-ramp ups. This model can
capture the “cascading sequence of causes and effects that determine how well a
company delivers against the key performance metrics of speed, quality, and cost”
(Mass & Berkson 1995, p.20-21). In this section, we will limit our discussion of the
model to the main goods flow structure and the key feedback loops that determine its
behavior over time.
Technically speaking, this model is a complex interrelated set of non-linear
differential equations. Because of space considerations, these are available from the
author in a separate document, both in text format as in simulation software format.
For ease of explanation, we will mostly use diagrams here that visualize the main
interrelations between variables. In Figure 2, a stock and flow diagram notation is
used (Sterman 2000), in which accumulations or state variables are symbolized by
rectangles, so-called “levels” or “stocks”, and rate-of-change or “flow” variables are
signified in the diagram as “pipes” with “valves.” In Figure 3, a causal loop diagram
notation is used, in which only the causal links and loops are shown between
variables, without distinguishing between different kinds of variables.
4.1. Main goods flow structure
The goods flow structure for the simulation model is shown in the stock and flow in
Figure 2. This is a simplified version of the supply chain structure shown in Figure 1.
In the case of a physical goods flow, the analogy with physical levels for the
rectangles denoting stock levels, and with the pipes with valves connecting them, is
obvious, but still the underlying mathematics are those of differential equations.
Upstream mig queue —_Upetream testing queue Transportation queue Downstream mig queue Downstream testing queva On the markst
@:
Upstream
production
: Downstream
Into transport production starts
Downstream
rg rate
Upstream
rig rate
Shipments
Downstoam rework
Upsttam rework
Downstream
reper
Downstream
pele fast fas
‘est fale
Downstream
Pit repairs repat fails
Figure 2: Overview of simplified supply chain structure in the simulation model
In the goods flow that is represented in the simulation model we will investigate, there
still is an upstream and downstream part of the supply chain, with a manufacturing, a
testing and a rework stage in both parts. In the downstream part of the chain, “the Pit”
reappears, which is a second-level of rework, for those units that could not be repaired
in the first-level rework stage. Components flowing in are not visualized, neither is
shown what happens to scarp. The clouds at the beginning and end of valves denote
system boundaries.
4.2. Main feedback control loops that drive dynamic behavior
A cornerstone of system dynamics modeling is the representation of feedback. During
the group model-building workshop that was conducted in the original field study,
four key feedback loops were identified that were felt to affect production
performance considerably. All are shown in Figure 3. There are two reinforcing
feedback loops identified in it, denoted R1 and R2, and two balancing feedback loops,
labeled B1 and B2. We will discuss these in this order.
Workforce
+
ey
Schedule
pressure -
Workload Production
A ya
Quality
Rework
Production
ws “ase
+
® Repairs
Figure 3: Key feedback loops in the model
RI: The accumulating workload loop: This reinforcing feedback loop
operationalizes the following line of reasoning. People tend to make more mistakes
when there is insufficient time to do a good job, i.e. when their workload is high.
Unfortunately though, these mistakes will lead to an accumulation of defective units
which, over time, will have to repaired. Repairs tend to require more - and higher
skilled - work time than normal production. Thereby, workload will increase
disproportionately, which will once again lead to more errors, etc.
In the model equations, the variable Workload is defined in a similar manner to
Oliva & Sterman( 2001) and Akkermans & Vos (2003) :
Processing required: _ WIPi* Work _content_ per _uniti
(Eq.1) : Workload: = . =
Processing _available: Workforcei* Wor ker_Pr oductivityi
(This formula applies to every one of the manufacturing, rework or testing stage,
hence the subscript i for stage i. )
Workload affects quality in the following manner, which assumes a so-called
“anchoring and adjustment process” (Einhorn and Hogarth 1981), common in
behavioral psychology model formulations:
(Eq.2) : Quality: = Average _quality:* f(Workloadi)
* f (Schedule _ pressurei)* f 3(Production _ Expertise)
Quality in a supply chain stage is equal to the current average quality in the stage
times an effect on that quality of workload and of schedule pressure and production
expertise, to which we will return shortly.
All these effects on quality are non-linear functions of the input variable. The
relation between workload and quality is a version of the Yerkes-Dodson law, which
posits an inverted U-shaped relationship between stress and performance on moderate
to difficult tasks (Yerkes & Dobson 1908, Fisher 1986, Eigen 1994).
The values for this curve that are used in this model are shown in Figure 4. This
graph shows that for normal workloads, between 0.75 and 1.25, there is no effect of
workload on quality, but for very low workloads of less than 0.5 and especially for
very high workloads of 1.5 and higher, the effect on quality becomes significant, up to
a degradation of 25% for workloads of 2.5 and higher. In the model, it is
conservatively assumed that this workload effects is only effective in the actual
manufacturing stages, not in testing, rework and transport stages.
1.25
$B, 00
§ c
z
3
6 0.75
0.50
0 0.5 1 1.5 2 2.5 3
Workload
Figure 4: Relation between workload and effect on quality
Finally, it should be noted that workload also affects detection likelihood in the test
centers in a similar manner, again via an anchor-and-adjustment type of multiplier
effect on the “normal” detection likelihood, which is set at 95% in the base case
version of the model.
R2. The schedule pressure loop. Quality is also negative affected by work
pressure. This reinforcing loop states that for high levels of work pressure, employees
will respond to work pressure by adjusting their behavior to meet throughput
expectations. This effect was empirically observed by Mass & Berkson and by Oliva
& Sterman (2001). The latter also empirically measured its effect. The feedback loop
reads as follows: the higher the work pressure, the lower the quality, hence the lower
the output, hence the higher the schedule pressure.
In the equations, Work pressure has as its input the % of market needs met, so:
T=t
100% * » Shipments:
——
rao Production _ starts:
(Eq.3): Perc__ MktNeeds_ Met: =
In this model, production starts equal the target ramp-up of marketing.
The slope of the curve of the function that translates values of work pressure
into an effect on quality is a monotonically increasing from 0.81 when 0% of the
market needs are met up to 1.0 when market needs are fully met for 100%.
B1. The workforce adjustment loop. Two key balancing feedback loops are also
shown in Figure 3. The first one is the workforce adjustment loop. In its general
meaning, this is a fairly straightforward one: when workloads rise beyond normal
levels, and after overtime has been exhausted as a buffer device, more employees will
be hired, with some dealy. Conversely, when there is not enough work for the current
workforce, people will be fired, again after a delay.
(Eq.4) : Desired _ workforce: = Experienced _ workforce:
+Inexperienced _Workforcei* f s(Workloadi)
This formula again applies to every stage in the production process. Workforce
consists of inexperienced and experienced employees, and only inexperienced
employees are hired. Initially, there is a 50-50% distribution of “rookies” and “pros”.
fs, the effect of workload on hiring, increases monotonically from 0.9 to 1.1. as
workload increases from 0 to 3 and beyond.
The rate equation for the hiring of new staff takes this desired rate into account,
after a delay of 4 weeks:
(Eq.5) : Change _in_workforcei = MAX (0,(Desired _workforcei
—Inexperienced _labori- Experienced _labori)/Hiring _ delay)
B2. The production expertise loop. The second balancing loop is less
straightforward. One good thing about repairs is that they tend to expose flaws in the
production process. Thereby, the more repairs are made, the more process expertise is
accumulated regarding the upstream production steps. In this way, more errors lead to
more repairs, which will lead to higher skill levels, which will reduce errors over
time.
This effect is different from a normal learning curve, which means that
productivity, defined as the # units processed per employee per time unit, goes up. A
learning curve is operationalized in the model through the flow of inexperienced
employees to experienced staff, after a 2 month delay. Inexperienced employees have
80% of the normal productivity, experienced ones 120%.
As Equation 6 shows, production expertise is accumulated by every repair, but
not all repairs carry equal weight, their relevance decreases over time and how
effective this insights is fed back to production operations also varies.
(Upstream _repairs* Insightgainedperrepair _Upstream
, Downstream _repairs * Insightgainedperrepair _ Downstream
(Eq.6) : Production _ Expertise = f +Pit _repairs* InsightgainedperPitRe pair)
° *Quality _ of _ feedback
*Timeliness_of _ feedback
The level of insight gained per repair upstream is only 20% of insights gained from
Pit repairs, which are much more complex and time-consuming as only the most
difficult cases end up in this rework stage. Similarly, downstream repairs account
40% of the insight a pit repair generates. Quality of feedback is set arbitrarily at 20%
in the base case (but subjected to sensitivity analysis in one of the policy scenarios
later on), and Timeliness of feedback degrades nonlinearly from | to 0 as these repairs
take place later on in the simulated 150 weeks of production.
4.3. Key performance metrics
To understand how this model behaves, we will have to pay special attention to most
of the variables that appear in the four feedback loops discussed above. But to
compare the performance of different quality management policies, we have to limit
our attention to a small set. This set of key performance indicators or KPIs is used in
the scenario comparison overview in Table 2 in Section 5. These KPIs are the
following:
- Average Output (in 000units/week): this is the average rate of shipments over the
simulation period (which is 150 weeks or 3 years).
- Average WIP (in 000 units): the sum of all inventory levels averaged over the
entire simulation period
- Average Workforce (in full-time equivalents or fte): the size of the total
workforce, inexperienced and experienced, over the entire simulation period
- Average Quality (in %): the quality level of outgoing products in the last internal
supply chain stage, which is downstream testing, averaged over the entire
simulation period. By quality level is meant here the percentage of products that
have errors in them that may or may not show up immediately. For finished
products, this translates to the likelihood that units will be in need of repair or
scrap over their technical lifetime, say 3 years. Anyone who used a computer in
the mid-nineties will acknowledge that a 25% likelihood of computer failure in 3
years time was not at all unrealistic. In the base case, our model shows an average
quality of 73%. This was also in line with internal company estimates in the
original field study.
- Average Cycle time (in weeks). This is calculated by dividing the total level of
units that are in the supply chain by the flow rate of units going out of the system,
which by Little’s Law gives the average cycle time (Hopp & Spearman 2000,
Sterman 2000). Or, in algebraic notation:
f Production _ starts: — Shipments:
(Eq.7) : Cycle _ time: = ©
Shipments:
In the manner, we have a fair overview of both financial performance indicators,
with shipment rate as a proxy for revenues and both headcount and WIP levels as
indicators for cost, and key operations performance indicators such as quality and
cycle time. This should enable a fair comparison of the pros and cons of the various
suggested performance improvements.
4.4. Base case behavior
Before we start analyzing the performance impact of the various structural and control
improvements contemplated by company management, let us first explore how this
model behaves in the base case. We start with a steep production ramp-up curve, as
shown in Figure 5. Production ramps up quickly, up to 10.000 units per week during
the peak period. After 90 weeks, or almost two years, there is no longer a market need
for additional units to be produced. By then, the next generation of PCs or laptops has
long been introduced. All in all, in some 400.000 units have then been put into
production.
100009 7
Units/week
50004
0. 1 1
0.00 30.00 60.00 90.00 120.00 150.00
Weeks
Figure 5: Production starts in base case
What does this inflow of new production starts result in? This is visualized in Figure
6. The peak in upstream productions starts returns here as the first data line, labeled
with “1”. One can observe how this inflow results in a delayed peak in upstream
manufacturing (line 2). However, this peak reappears with a delay and considerably
less prominent in the next stage downstream, which is visualized by the line “into
transport”, labeled with “3”. [We will soon see that this is because a large portion of
the units produced is found to be defective and ends up as rework.]. Downstream
manufacturing can deal with the inflow from upstream quite well, it would seem from
the behavior or “4”, the downstream manufacturing rate, which is quite similar to line
4. And yet, the shipment rate of finished product into the market (“5”) is much
smoother than the downstream manufacturing rate. Again, we will see that this is
because of defective units as a result of poor process quality in manufacturing.
At 2: 3 4 5:
Upstream Upstream Transport Downstream Shipments
Mfg starts Mig rate rate Mfg rate To market
15000°
Units/
week
7500:
7 4y
su eres |
o+ 1 123.
0.00 30.00 60.00 90.00 120.00 150.00
Figure 6: Key upstream and downstream product flow rates in the base case
The line in Figure 6 shows how the peaks that still exist in upstream process stages
gradually disappear. Line “1”, which visualizes the number of upstream test fails per
week, peaks towards 5000 units after 1 year, which explains the bulk of the difference
between upstream manufacturing and transportation to downstream in the preceding.
Interestingly, it takes the upstream rework case a long time to repair these units. The
peak in the upstream repair rate (line “2”) is some 40 weeks later. Similar phenomena
can be observed downstream as well. There is a peak in downstream test fails (Line
“3”) around 60 weeks that explains why so much less is shipped to customers than is
leaving downstream production in this period. One difference with upstream is that
here we have two rework stages. When downstream repair fails (Line “4”), the
defective units automatically end up in the 2™ line rework stage called “the Pit”,
whereas they remain in the 1" line rework stage for the upstream part of the chain.
Hence, downstream repairs peak in the pit (Line “5”) and, again, after a very
considerable time delay.
ot)
ie z 3 4 5:
Upstream Upstream Downstream Downstream Pit
Test fails Repairs Test fails Repair fails Repairs
60007
Units) 4
week
30007
Figure 7: Output rates in test and rework stages in the base case
Why are there towards the end of the first year such high test percentages of units
both upstream and downstream? That has everything to do with workloads. We
already saw that higher workloads lead to lower process quality and hence to more
errors detected and, thereby, to less output of product and instead more rework.
ite 2 i
Workload Workload Workload
Upstr Mfg Upstr Test Upstr Rew
207
200
Workload
[Dimensionless]
100
—
0.00 30.00 60.00 90.00 120.00 150.00
Weeks
Figure 8: Upstream workloads
This becomes quite apparent from the graphs in Figure 8 and Figure 9 where the
behavior of workload per stage is shown. In both upstream and downstream
manufacturing, processing capacity is simply not able to deal with the ever-rising
inflow of new units to be processed and so workloads (lines labeled “1” in both
graphs) rise to very high levels. Workforce is increased, but just not fast enough to
keep up with the rise in workload.
71
As we saw in Figure 6, the peak inflow in upstream manufacturing is higher
than that in downstream manufacturing, and so the workload levels are similarly
different: up to 15 in upstream manufacturing, yet near 4.8 in downstream
manufacturing. Workloads in the test stages (lines labeled “2” in both graphs) are not
so badly capacity constrained, since the work content for testing is considerably less
than for manufacturing. What they are faced with is a recurrent inflow from reworked
units that first failed testing. But in the testing stages, processing capacity is far more
capacity constrained, since it takes much longer to figure out what is wrong with a
unit and fix it than to “do it right the first time”. Workloads for rework stages (lines
“3” and “4” in these graphs) have to be scaled much higher, since these peak at
around 100.
1 2 3 4:
Workload Workload Workload Workload
Downstr Mfg Downstr Test + Downstr Rew The Pit
200
Workload
[Dimensionless]
100
120.00 150.00
Figure 9: Downstream workloads
Almost by definition, the process quality in each of these stages must drop if
workloads become too high. This fits with the graph in Figure 10 that shows quality in
both upstream and downstream testing stage, just before the products go into
transport. Again, one can witness the effects of the peak in production in the second
half of the first year here, with upstream quality dropping to a low from week 30
onwards but recovering strongly after week 60, and with downstream quality
dropping later, after week 50, but more steeply, and recovering somewhat later. The
lower quality level in the third year is attributable to the high rework levels in the
downstream part of the chain during that period. After all, no new units are released
into upstream production after week 70, so in the upstream stages most of the
negative workload effects have ebbed away by this time.
9
e 2
Quality Quality
In Upstream rr
7" test stage Downstream
Test stage
2°
Quality 7 2. 2. <a {
[Dimensionless] 2:
0.00 30.00 60.00 90.00 120.00 150.00
Weeks
Figure 10: Quality in upstream and downstream test stage
Figure 10 shows us how this supply chain performs in terms of quality. How does this
base case scenario do in terms of our other pre-defined performance criteria for
output, cost, and time? Here we can look at Figure 11. We see total output to the
market displaying the kind of S-curve growth pattern typical of product life cycles.
The behavior of total inventory is proportional to the amount of product being pushed
into the supply chain, with a significant delay in its peak level compared to the peak
in production starts.
The workforce also responds with a delay to the increase in processing
requirements, but does not really drop off again, partly because of inflexibilities in the
labor force, and partly because rework requirements, which are very labor-intensive,
remain considerable until very late in the simulation. Cycle time first grows in line
with the growth in WIP, as Little’s Law would make us expect, but there is a drop and
then a renewed peak in the third year as a disproportionate percentage of the
remaining units in the supply chain is rework, which is far more time consuming than
regular processing. In comparison: regular manufacturing stands to testing, stands to
regular rework and to pit rework as 6:1:8:25 (based on company data).
m2
1: 2: 3 4:
Total Market Total Total Total
Output Inventory Workforce Cycle time
4000004
200000
350
7 en
Units 1
Units 4 “
Fte |
Weeks
200000
100000.
250
38
0
9 4
150
04 ‘ t
0.00 60.00 90.00 120.00 150.00
Weeks
Figure 11: Behavior of key output performance criteria (excl. quality)
Average values for these performance indicators are presented in Table 2 below,
where the performance outcomes of the various improvement scenarios that will be
discussed next are compared against each other.
5. Scenario and policy analysis
In this section, we explore policies that aim to improve the performance of the supply
chain on all levels, but with specific attention to quality, as this is clearly one of the
key determining factors for all other performance dimensions (and the focus of this
paper).
# =~ Scenario Name Average Average Average Average Average
Output WIP Workforce — Quality Cycle time
(000u/wk) (000 units) (fte) (%) (wks)
0 Base case 2.35 58.7 250 73% 43
1 Modest ramp-up 2.53 32.3 228 78% 28
2 High component quality 2.46 47.1 259 77% 37
3 High upstream quality 2.40 55.1 258 73% 44
4 High downstream quality 2.54 35.1 251 78% 21
5 High error detection 2.34 61.4 248 74% 44
6 Upstream info feedback 2.42 55.4 252 77% 41
7 Add Pit staff 2.37 41.9 276 77% 25
8 High quality gate (75%) 0.58 132.2 225 51% 169
9 Modest quality gate (65%) 2.36 58.7 249 74% 42
10 Combination of 6 & 7 2.45 38.8 276 82% 22
11 Combination of 5,6,7 & 9 2.45 39.9 275 83% 23
12 Combination of 1,6 & 7 2.58 18.2 246 83% 11
Table 2: Summary of performance impact of different policy scenarios
94
5.1 Modest versus aggressive ramp-up
One of the quality management measures that was not under serious consideration
was a more aggressive production ramp-up schedule. Company management that
being first on the market was really a strategic imperative for the company, and that
this could only be achieved by stressing the supply chain to the limit. However, also
an earlier study with the same company had suggested that taking the raw edge off
production ramp-ups might have very beneficial results for the product development
area (Mass & Berkson 1995).
As Figure 12 shows, the notion of “going slow to go fast” also applied to the
manufacturing supply chain. The line labeled “1” shows production starts under the
“normal” fast ramp-up, the line labeled “2” shows how the same total product volume
could be brought into the supply chain but with a more moderate growth rate.
What company management expected, was that a slower ramp-up of inputs to
the supply chain, would also lead to a slower output growth of the chain. But what
Figure 12 suggests, is that the opposite is the case. The line labeled “3”, which is the
output rate under the aggressive ramp-up regime, actually is slower in bringing
finished product to the market than line “4”, the output rate under the moderate ramp-
up regime.
1 2 3 4
Start rate- Start rate- Shipments- Shipments-
fast ramp- Moderate Fast Moderate
up Ramp-up ramp-up Ramp-up
10000
Units/week
5000
150.00
Weeks
Figure 12: Comparison of in- & output rates for fast and moderate ramp-ups
Moreover, Scenario 1, as this is called in Table 2, considerably outperforms the base
case with the fast ramp-up on every aspect of performance. Not surprisingly, this
scenario was difficult to digest for company management during the original field
study.
5.2 High component quality
Less controversial was the outcome for Scenario 2, the high component quality
policy. In this scenario, both upstream and downstream component quality is
increased from 90% to 99%. Getting such a policy implemented was the harder part
of this scenario, obviously, as this would require significant coordination with
component suppliers, if it was technically feasible at all.
oy
5.3 Consistently high manufacturing quality
Another scenario that made intuitive sense to management as it resonated thoughts
from lean or TQM as it was called at the time, was to redesign manufacturing
operations such that quality of the output would become virtually independent of
workload and worker skill-level, for instance through the use of fail-safe equipment.
As this would require major redesign and employee training, this was thought to be a
very costly policy and one for the longer term, but still one important enough to
evaluate through the modeling effort.
What was not intuitively clear was where such manufacturing quality
measures would pay off most: upstream, downstream or both. Scenarios 3 and 4 in
Table 2 provide us with a preliminary answer: downstream quality improvements
yield far more benefits than upstream ones. In both scenarios, quality in the actual
manufacturing stage is fixed at 98%. Which is somewhat counter-intuitive, one might
argue, as doing-it-right-the-first-time would imply high quality upstream. At least this
was the finding from Akkermans & Vos (2003), where high service quality upstream
was found to be crucial for high quality throughout the chain.
Model analysis suggests that this is because of workload effects. With high
upstream quality your output becomes somewhat higher, because during the peak
there is more output from upstream to downstream, but this also results in higher
workloads downstream and therefore actually marginally lower quality delivered than
in the base case (72.9% versus 73.2%).
5.4 Superior error detection
At the time of the original field study, company management was considering
investing in better error detection equipment. The results from Scenario 6 suggests
that this is not a high-leverage investment. There is some improvement, but only
marginally so. Model analysis suggests that this is because in the base case, detection
likelihood is already fairly high, at 95%, and workload effects are relatively limited in
size, so there is relatively unused improvement potential to address, even with a
detection likelihood of 99%.
5.5 Improve upstream info feedback & add experienced Pit staff
Company management puzzled about what to do with the defective units in “the pit”,
as it was evocatively called internally. On the one hand, this was just stuff taking up
factory space. On the other hand, management realized that hidden somewhere in this
pile, there could lay the answers to many of the thorniest quality issues. So, there was
genuine interest in seeing what could be done in this area.
The modeling team looked at two related aspects of doing more with Pit
inventory. Scenario 6 shows what would happen if far more attention would be placed
on feeding back insights from repairs to upstream manufacturing. Since the upstream
part of the supply chain was located at a different site, and given the extremely high
work pressures, especially during the early stages of the ramp-up, this happened only
sporadically and piecemeal. What if information feedback would really be addressed
thoroughly?
In this scenario, the quality of info feedback is changed from 0.2 to 1.0, soa
considerable increase indeed. But the pay-off might also be considerable, as the
performance outcomes of this scenario in Table 2 suggest. On the KPIs of output rate
os
and quality delivered, this policy shows up as being just as effective as the next policy
alternative, Scenario 7, which suggests adding 10 experienced workers to the Pit staff,
a fairly costly measure on a total of 200 fte. The information feedback scenario
clearly outperforms the additional Pit resource policy of Scenario 7 in terms of
workforce but is less effective in reducing WIP and cycle time. Why this difference
occurs is fairly straightforward. More experienced staff in the not only leads to more
and more timely feedback on quality issues upstream, but also to far more units
repaired. And that means lower stock levels and, by definition, lower cycle times. A
combination of both scenarios would even be more promising, as we will see in
combination scenarios 10-12.
5.7 Quality gates, both high and modest
The discussion between modelers and company management on the effectiveness of
quality gates, or “phase gates” as checks of product quality was an especially difficult
ones. This was and continues to be a popular practice in many industries and is very
much in line with lean/TQM thinking. In the words of Mass & Berkson (1995), “A
quality gate is a hard screening and rework point beyond which products cannot pass
until they are upgraded to at least the gating quality level”. At least these authors
found that during the early stages of product development, when quality levels are
really low, so under 50%, such quality gates have benefits, but they too had found that
“downstream quality gates add progressively less value and can eventually destroy
value. (..) a quality gate positioned behind the prototype stage or in integrity
testing is worse than no quality gate at all” (Mass & Berkson 1995, p.24).
Why is this? Because when the quality gate is set too high, workloads reach
levels that go beyond the tipping point and upstream manufacturing gets caught in an
almost never-ending recycling of low quality and huge rework rates, from which it
cannot escape through superior insights from downstream repair work. In essence, it
is simple: every week, new units are put into production, driven by the ramp-up
schedule, but no units are leaving the production stage. So, work in progress and
hence workloads keep piling up, far faster than the workforce can grow to
accommodate it.
O77
fl 2: 3 4:
Quality Quality Quality Quality
Gate of Gate of Gate of Gate of
60% 65% 70% 75%
60004
Shipments
(Unitsiweek) J Fs
0.00 30.00 60.00 90.00 120.00 150.00
Weeks
Figure 13: Impact of different quality gates on shipment rate
Figure | shows the impact of different gating quality levels. At 60%, line “1”, there is
effectively no quality gate since quality never drops below 64% in the base case. At
65% (the line labeled “2”), there is actually some improvement over the base case
(Scenario 9 in Table 2). Although there is a brief drop of output around week 55, this
helps somewhat in making downstream workload levels rise further, almost as a kind
of Input-Output control (Wight 1970, Hopp & Spearman 2000). In this way, average
output rates and quality levels are marginally higher than in the base case.
Line “3” shows the dramatic effects of increasing the gating quality level too
high. At week 40, in the peak of the production ramp-up, the quality gates prevents
product flows to downstream and it takes the supply chain until the end of the
simulation to recover. When the gating quality is raised to 75%, as is illustrated by
line “4”, the supply chain never recovers.
Clearly, in these last two scenarios, the system has been moved beyond its
tipping point, as Repenning et al. (2001) also found for product development projects
in which fire-fighting became the rule. As these authors formulated this, “In models
of infectious diseases, the tipping point represents the threshold of infectivity and
susceptibility beyond which a disease becomes an epidemic” (Repenning et al., 2001)
Similarly, in supply chains there exists a threshold for quality levels that, when
crossed, causes a vicious cycle of low quality leading to high rework leading to high
workloads leading to low quality to spread rapidly to the entire supply chain, in this
case the upstream part of the chain.
5.10.Combined policies
Scenarios 10 tot 12 show how a combined policy can yield superior results. Scenario
10 shows that leveraging the Pit and the production knowledge that repairing its
content can give is really a worthwhile endeavor, with an average quality level of
82% and an average cycle time of almost half the value for the base case. Scenario 11
shows that not every combination adds value. Better error detection and a modest
quality gate don’t significantly improve the performance of the supply chain. The last
IR
combination of policies, Scenario 12, adds to the Pit leverage policies the notion of
the moderate ramp-up. This is clearly a very successful scenario, with superior
performance on every aspect. Moreover, it does not require major investments (not
even in workforce), but primarily a different managerial attitude towards marketing
and knowledge management.
6. Propositions
What do these experiments tell us regarding the topic of this paper, effective quality
management (QM) during production ramp-up in supply chains? Of course, several
caveats need to be made regarding validity and generalisability. Nevertheless it is
hoped that the combination of an in-depth case study, a fairly generic model and a
closely aligned set of relevant causal relations from behavioral psychology provides
sufficient triangulation opportunities to give credibility to our findings.
We must remain cautious with drawing far-reaching conclusions regarding
specific policies on the basis of the specific outcomes of these policies in this specific
model. After all, much will depend on specific parameter values and initial values of
variables. Nevertheless, it seems appropriate to suggest the following four
propositions:
Proposition 1. /Single point solutions don’t work]. Effective QM policies during
production ramp-up will use smart combinations of different policies that reinforce
each other. “Rounding up the usual suspects” is almost certainly a sub-optimal
solution.
Proposition 2: [Keep away from the tipping point.] Effective QM policies during
production ramp-up will ensure that workload levels in supply chain stages do not rise
so high that the entire chain gets bogged down in a vicious cycle of high workloads,
low quality levels, high rework levels and hence even higher workloads.
Proposition 3: [Go slow to go fast.] Effective QM policies during production
ramp-up will avoid frontloading the supply chain with so much extra work that the net
result is that product comes out slower, rather than faster, compared to a more
moderate production ramp-up.
Proposition 4: [Get out of the pit]. Effective QM policies during production
ramp-up will ensure timely downstream feedback on hidden upstream quality issues
through
(a) releasing enough low-quality WIP early
(b) adequately resourcing downstream repair, and
(c) comprehensive and timely feedback.
Conclusions
This study has looked at the highly dynamic issue of managing quality during
production ramp-ups in high-tech supply chains. It has based its analysis on an in-
depth case study of one particular high-tech supply chain setting. It has benefited from
insights from the recently-emerging literature on behavioral operations, in particular
on the interrelations of workloads, quality levels, schedule pressures, rework levels
29
and production knowledge that appear to be at the core of this issue. It has combined
the field data and the theory into a more general system dynamics simulation model of
such as supply chain setting to explore the relative contribution of different policy
options for effective quality management.
Fundamentally, what this study illustrates is that “rounding up the usual
suspects” to select such policies is a perhaps understandable but very dangerous
managerial attitude. This study agrees fully with Mass and Berkson (1995) when they
state that: “Often, the problem is a failure to consider [the supply chain] as a dynamic
whole. Managers try to improve performance by breaking the process apart. What’s
needed instead is an integrated, holistic approach that captures [the high-tech supply
chain] as a complex system. It must recognize and account for the cascading sequence
of causes and effects that determine how well a company delivers against the key
performance metrics of speed, quality, and cost.” (Mass & Berkson 1995, p. 20-21).
When behavioral psychology, operations management and system dynamics
simulation join forces to address this challenge, it might just be the beginning of a
beautiful friendship...
Acknowledgements
This paper is dedicated to the memory of Nat Mass, who originally made this research
possible. Sincere thanks go to Kim van Oorschot (INSEAD) and Paulo Gongalvez
(University of Miami) for their helpful comments and suggestions.
References
Akkermans H.A. (2001) Renga: a systems approach to facilitating inter-organizational
network development. System Dynamics Review 17: 179-193.
Akkermans, H.A., Vos, C.J.G.M. (2003): Amplification in Service Supply Chains: An
Exploratory Case Study from the Telecom Industry. Production and Operations
Management 12(2), 204-223
Akkermans, H.A. & van Oorschot, K.E. (2005) Relevance Assumed: A Case Study of
Balanced Scorecard Development Using System Dynamics. Journal of the
Operational Research Society 56, 931-941.
Anderson, E.G. & Joglekar N.R. (1996) Modeling the Dynamics of Technological
Ramp-up within Firms. 1996 International System Dynamics Conference,
Cambridge, Massachusetts, System Dynamics Society.
Anderson, E.G. & D.J. Morrice. 2000. A Simulation Game for Service-Oriented
Supply Chain Management. Production and Operations Management 9 (1): 40-
55.
Anderson E.G., Morrice D.J. & Lundeen G. (2005) The physics of capacity and
backlog management in service and custom manufacturing supply chains. System
dynamics Review 21(3), 217-247.
Boehm, B. & Turner, R. (2005). Management Challenges to Implementing Agile
Processes in Traditional Development Organizations, IEEE Software 22 (5), 30-
39.
Boudreau, J. Hopp, W., McClain, J.O. & Thomas, L.J. (2003) On the Interface
Between Operations and Human Resources Management. Management of Service
Operations 5(3), pp.
Eigen, K.H. (1994) “Yerkes-Dodson: A law for all seasons.” Theory and Psychology,
an
4: 525-547.
Einhorn, H., R. Hogarth. (1981) Behavioral decision theory: Process of judgment and
choice. Annual Review of Psychology 32 53-88.
Evans, G.N., Naim, M.M. & Towill, D.R., (1998) Application of a simulation
methodology to the redesign of a logistical control system. /nternational Journal
of Production Economics 56-57, 157-168.
Feigenbaum, A.V. (1961) Total quality control: Engineering and management.
McGraw-Hill, New York.
Fine, C. H. (1998). Clockspeed: Winning Industry Control in the Age of Temporary
Advantage. Reading, Mass., Perseus Books.
Ford, D. N., & Sterman, J. D. (1998). Dynamic Modeling of Product Development
Processes. System Dynamics Review, 14(1), 31-68.
Ford, D. & Sterman, D., (2003). The Liar’s Club: Concealing Rework in Concurrent
Development. Concurrent Engineering, 11(3), 211-219.
Gino, F. & Pisano, G. (2006): Behavioral Operations. Harvard Business School
Working Paper, Version February 3, 2006.
Glaser, B. & Strauss, A., (1967) The Discovery of Grounded Theory: Strategies of a
Qualitative Research. Wiedenfeld and Nicholson, London.
Gongalves P., Hines J. & Sterman J. (2005) The impact of endogenous demand on
push-pull production systems. System dynamics Review 21(3), 187-216.
Hall, R.W.(1987) Attaining manufacturing Excellence. Dow-Jones Irwin, Homewood III.
Holweg M., Disney, S.M., Hines, P. & Naim, M.M., 2005. Towards responsive
vehicle supply: a simulation-based investigation into automotive scheduling
systems. Journal of Operations Management 23, 507-530.
Hopp, W.J. & Spearman, M.L. (2000) Factory Physics. Irwin McGraw-Hill, Boston.
Tansiti, M., & MacCormack, A., (1997) Developing Products on Internet Time,
Harvard Business Review, September-October 1997, pp.108-117
Juerging, J. & Milling P.M. (2006) Manufacturing start-ups in the automobile
industry. Proceedings International System Dynamics Conference, Nijmegen, July
2006. Accessible at www.systemdynamics.org
Karlstr6m D. & Runeson, P. (2005): Combining Agile Methods with Stage-Gate
Project Management. IEEE Software 22(3), 43-49.
Morris, B (2006) “Tearing up the Jack Welch playbook”. Fortune June 11, 2006.
Kennedy, M.N. (2003) Product development for the lean enterprise. Thee Oaklea
Press, Richmond VA.
Mass, N.J. & Berkson, B. (2005) Going slow to go fast. McKinsey Quarterly 1995(4),
19-29.
Miles, M.B., Huberman, A.M. (1984) Qualitative Data Analysis: A Sourcebook of
New Methods. Sage, Beverly Hills,
Molokken-Ostvold, K. & Jorgensen, M. (2005): A Comparison of Software Project
Overruns-Flexible versus Sequential Development Models. JEEE Transactions
on Software Engineering 31(9) 754-766.
Ohno, T. (1988) Toyota Production System. Beyond Large-Scale Production.
Productivity Press, New York. Originally in Japanese: Toyoto seisan hohshiki
(1979) Diamond, Inc, Tokyo.
Repenning, N. (2001). Understanding Fire Fighting in New Product Development,
Journal of Product Innovation Management, 18(5), 285-300.
Repenning, N. (2002). A Simulation-Based Approach to Understanding the Dynamics
of Innovation Implementation. Organization Science, 13(2), 109-127.
al
Rudolph, J.W. & Repenning, N.P. (2002) Disaster Dynamics: Understanding the Role
of Quantity in Organizational Collapse. Administrative Science Quarterly, 47
(2002): 1-30
Schonberger, R.J. (1982) Japanese manufacturing techniques. Nine hidden lessons in
simplicity. Productivity Press, New York.
Sterman, J.D. (1989) Modeling managerial behavior: Misperceptions of feedback in a
dynamic decision making experiment. Management Science. 35, 321-339.
Sterman, J.D. (2000) “Business Dynamics: Systems Thinking and Modeling for a
Complex World.” Chicago, IL, Irwin-McGraw Hill.
Takeuchi, H. & Nonaka, I. (1984) The new product development game. Harvard
Business Review Jan-Feb 1984, pp.137-146.
Vennix, J.A.M. (1996) : Group Model-Building. Facilitating Team Learning Using
System Dynamics. Wiley, Chichester.
Wight, O. (1970) “Input/output control: A real handle on lead time”. Production and
Inventory Management Journal 11(3), 9-31.
Womack, J.P., Jones, D.T. & Roos D. (1990) The machine that changed the world. Simon
& Schuster, New York.
Yerkes R.M. & Dodson J.D. (1908) The relation of strength of stimulus to rapidity of
habit formation. Journal of Comparative Neurological Psychology 18: 459-482.
29