WATER RESOURCES DEVELOPMENT PLANNING
By
Ali N. Mashayekhi
Department of Industrial Engineering
Sharif University of Technology
Tehraa, Iran.
March 1989
ABSTRACT
Water resource development requires development and operation of expensive
facilities. Planning, design, and execution of water resource projects in Iran have been
taking a period of time much longer than what is considered as a normal time. In
addition, the projects are costing much more than normal, This paper presents a system
dynamics model to analyze the behavior of the water resource development system. The
paper shows that high cost and Jong construction time are results of policies that
govern decisions related to budget allocation, start of new projects, and price of water.
The paper shows that how alternative policies could improve the behavior of the
system, It is argued that appropriate planning approach for, water resource
development should consider the feedback mechanism in the water resource
development system and concentrate on design policies that control the behavior of the
system through those feedback loops.
INTRODUCTION
Water resource development requires construction and operation of expensive
facilities such as dams, channels, and drainage system. Each year billions of Rials in
Iran are spent in feasibility studies, design. construction, and operation of such
facilities. Planning and budgeting of water resource development tend to be based on a
traditional approach in which goals are set, programs to achieve the goals are
developed, and the resources to implement the programs are requested.
However, water resource development is not taking place effectively and
efficiently. Projects completion time and cost are much larger than originally planned.
In order to improve the development effectiveness and efficiency in the water
industry, planning and control processes should be changed. High level management
should focus on design and implementation of a new planning system in which
attention is paid to the feedback loops which control the behavior of the system. The
new system should identify the important contro! points in the feedback loops and
provide appropriate rules to regulate the whole system from such control points in an
effective and efficient way.
A system dynamics model is developed to help management in designing
appropriate decision rules in order to improve the behavior of the water development
system. The model is presented in this paper and behavioral results of different policies
or decision rules are examined.
642
WATER RESOURCE DEVELOPMENT SYSTEM
Water system consists of five sectors: water supply facilities to control surface
and ground water resources , distribution channels which transfer water from supply
facilities to agricultural lands, transfer pipelines which transfer water from supply
facilities to city distribution network, city water refinery and distribution network, and
water sewages.
* Development of new facilities, as shown in Figure 1, consists of planning,
feasibility study, design, construction,.and operation
WATER RESOURCE DEVELOPMENT PERFORMANCE
Performance of water resource development has not been satisfactory in Iran.
The completion time of projects has been long. Currently, the ratio of the amount of
Money needed to complete the projects under design and construction to the annual
development budget of the water system.is about 75 years (4). The value indicates that
in terms of available money it will take on average about 75 years to finish current
Projects which is much longer than the normal time.
Low budget relative to what is required and long construction period would
increase project costs. When a project starts, it will have some fixed cost. The fixed cost
occurs as long as the project continues. When the completion time increases, the total
fixed cost of the projects rises and projects become more expensive. As projects become
More expensive, with a certain amount of budget fewer projects can be finished and
less amount of water resources can be developed.
Long construction period and high construction cost are indication of low
performance of water resource development. Such low performance is due to planning
approach in which feedback loops are not considered (3) and policy design is not the
focus of the planning.
A SYSTEM DYNAMICS MODEL FOR WATER DEVELOPMENT PLANNING
Overall Structure
Water development system consists of five different sectors: Water supply
facilities, water distribution and draining channels, water transfer facilities to cities,
city water distribution facilities, and city water swages facilities. As shown in Figure 1,
development of each sector consists of five stages: Development planning, feasibility
study, engineering design, project construction, and operation.
Flow of projects through different stages in each sector can be conceptualized
by a series of rate and level variables (1&2). Figure 2 shows the flow of projects during
development process for water supply facilities. The flow of projects in other sectors of
water development system is similar to what is shown in Figure 2.
Major Decision Points
In Figure 2, rate variables represent decision points in the system.
643
Major Decision Rules:
For the sake of simplicity, in this paper, only two sectors are considered. Some of
the major decision rules in these two sectors are the followings.
Allocation of Budget Between Different Sectors:
Completion rate of projects in different sectors and stages depend on the
allocated budget to those sectors and stages. Two alternatives for allocation of total
budget between water supply and water distribution sectors are considered, Total
budget is allocated proportional to the desired budget in each sector. In one alternative
which is in accordance with the current policies, the desired budget in each sector is
determined based on work in process in different stages of that sector. Alternatively,
the desired budget can be determined to bring in balance the capacities of water supply
and water distribution sectors,
Starting Rate of Projects in Different Stages
Another major decision rules are related to the starting rate of projects in
different stages. The starting rate of feasibility study is based on the difference
between the forecast of demand for water and water supply projects under study,
design, construction, and operation. The starting rate also depends on the ratio of
allocated budget to desired budget for water supply sector. A lower budget decreases the
starting rate.
The starting rate of projects in design and construction stage, according to
current policies, are proportional to feasible projects and designed projects. It is
assumed that on average 6 months after feasibility study is completed, design stage
starts and 6 months after design stage is completed, construction phase starts.
Another alternative is to formulate starting rate as a function of the amount of
available budget to finish projects under design or construction relative to the desired
budget to finish those projects during a normal time. Under this alternative, the
Starting rates depend on available budget and projects in the previous stage. If all the
desired budget is allocated then starting rates are a constant fraction of projects in the
peers stage. When all required money is not available, them starting rate is
Inactivating Rate of Work in Construction Stage
Another policy governs the inactivating rate of projects under construction.
Under one policy alternative, inactivating rate is zero. Under another alternative,
inactivating rate is a function of desired projects under construction relative to actual
projects under construction. Desired projects under construction is a function of
allocated budget for construction projects. When projects become inactive, their fixed
cost decreases to a lower fevel relative to when they are active. In addition, inactive
Projects do not require any variable budget which make construction progress
possible.
644
Pricing Policy.
Another decision point that is not shown on Figure 2 is pricing decision.
Currently the nominal price of water is constant. Under current pricing policy the real
price of water decreases when inflation raises the general price index. Alternative
pricing policy can be adopted.
Cost Structure in Construction Stage
In construction stage two kinds of cost are recognized: fixed cost and variable
cost. Fixed cost is the minimum annual budget that is required to keep construction
projects for one unit of water supply capacity ready for physical progress. The second
kind of cost is variable cost. The variable cost is the cost that should be paid to finish
construction of one unit of water supply capacity. Average unit cost of water supply
projects is unit variable cost, which is constant, and average accumulated fixed cost for
unit of water supply capacity. When duration of construction rises, accumulated fixed
cost increases and raises the unit cost of the projects.
MODEL BEHAVIOR AND POLICY DESIGN.
The Base Run
The base run shows the behavior of the model under current policies. Policy
assumptions of the base run are: (1)_Budget allocation between different sectors and
different stages is based on desired budget for work in process in the sectors and stages.
(2) Starting rate of projects in different stages is based on the amount of projects in
the previous stage. (3)_Inactivating rate of the projects in the construction stage is
zero. (4)_Price of water is constant. (5)_Starting rate of feasibility study is a function of
discrepancy between projected demand for water and sum of water supply capacity
under operation, construction, design, and study. The starting rate also depends on the
allocated budget relative to the desired budget.(6)_Total development budget for water
facilities is constant after 1985. With the base run policies the behavior of the model is
shown in Figure 3.
In the base run, because of the pressure from demand, starting rate of
feasibility study increases and raises the number of feasible projects. Feasible projects
Move automatically forward into design stage and finally construction stage. Projects
under construction increases. When projects under construction increases, fixed cost to
keep projects ready for progress in construction rises. When total budget is constant
and fixed budget increases, then remaining budget for construction work decreases
and completion rate of projects under construction fall. When completion rate falls,
projects under construction rises more rapidly and causes fixed cost to increase to a
higher value, As fixed cost rises, unit cost of projects increases. With higher unit cost
and a constant development budget fewer projects can be completed.
New Policies for Starting Rates
In this section relative to the base run, some addition factors affect the starting
rate. The starting rate of feasibility study is adjusted based on feasible projects relative
to the average starting rate of engineering design. When feasible projects relative to
the start of design increases, which means enough feasible projects are available to
feed design activities, then start of feasibility decreases. Similarly, the starting rate of
design is adjusted based on designed projects relative to the start of construction. The
645
starting rate of construction is adjusted based on available budget. When allocated
budget is less than desired budget, starting rate decreases and vice versa. The behavior
of the modei with this new policy is shown in Figure 4.
Because the starting rates of feasibility study and design are adjusted based on
feasible projects and designed projects, respectively, and the start of construction is
adjusted based on available budget, the system should not be overloaded with projects as
much as in the base run. However, still pressures from demand causes the new projects
to be started and accumulation of projects in the construction stage increases the total
fixed cost and decreases the completion rate. As a result, the behavior of the system is
not much different from the base run.
Inactivating Policy
In this section in addition to the new starting rate policies, some of the projects
in construction stage are inactivated when the available budget is less than desired.
Inactivated projects have a lower fixed cost relative to active projects. Inactivated
Projects are activated when insufficiency of budget disappears. No construction
activities take place in inactivated projects and therefor no money is spent as variable
cost. The behavior of the model with new policies is shown in Figure 5.
Inactivating of excess projects under construction decreases fixed cost of
projects under construction. Lower fixed cost lets more money available for
construction activities and increases completion rate of the projects.
A Higher Price for Water
In this section, in addition to starting rate policies and inactivating rate policy,
the price of water is increased. The behavior of the model is shown in Figure 6. Higher
price of water increase the amount of money available to the water development
system. As a result completion rate increases and let the water supply facilities to rise
during the simulation.
REFERENCES:
1. Richardson G. and Pugh J., Introduction to System Dynamics Modeling with DNAMO,
MIT Press, 1980.
2. Richmond, et al., Computer Simulation, An Academic User's Guide to STELLA, High
Performance System, 1986.
3.Sterman J.D. 1987, Misperceptions of Feedback in Dynamic Decision Making,
Organization Behavior and Human Decision Processes.
4. Mahabe Ghods, 1989, “Niazhaie Tarhaie Omrani Ab", in Farsi, Mahabe Ghods.
Figure 1: Stages of water development system in each sector.
646
ip
Start of Feasibility Study
from Unplanned Projects
SS
ff >| opp PUFWS
i Planned Projects com
Projects Under
Development Start of Study Completion.
Planning Feasibility Rate of
Study from Feasibitity
Planned Projects
c—| vpws | pupws [# FPWS
Designed ceDws Projects /SEDWS Feasible
Projects Under Projects
Comptetion Design Start of
Rate of Engineering
Engineering Design
Design
Inactive Projects
Under Construction} IPCWS
Inactivating Rate
Activating Rate | ARCWS IRCWS | of Construction
of Construction Projects
Projects
SJ
> pucws —P puows 5
ire (sc
Projects Water
Startof Under Completion Supply Depreciation
Construction Construction Rate of Facilities
Construction
Figure 2: Flow of projects in water development system.
@.
15.e9 1975. 1985, 1995. 2005.
TIME
Figure 3: The Base Run: Behavior of Water Supply Facilities.
Swen ee ieee
a.
15.29 1975. 1985, 1995. 2085.
TINE
Figure 4: New Policies for Starting Rates: Behavior of Water Supply Facilities.
648
15.05 1975. 1985, 1995, 2085.
TIME
Figure 5: Inactivating Excess Construction Projects.
INIT Cos FoR conraucTLO 0 .(28,0-3, 1)
COMPLETION’ TAME OF WATER SUP. CONE PROJECTS CSB. 7
COMPLETLON RATE OF GATE SUPBLYFACKLITLESC@s L000: 6)
"MATER SUPPLY FACI LITIES(15.09,.5.e9)
iia Teg
ws,
% —
are [
we .
ia Sea
Pee]
—_—— —— ee
5.8 1975, 1985. 1995. 2005.
TIME
Figure 6: A Higher Price for Water.