“Integrative Mechanisms in New Product Development
Projects: Effect of Project Complexity on Project Performance
A System Dynamics Approach”
Reda M LEBCIR
Imperial College Management School
53 Princes Gate, Exhibition Road, London SW7 2PG, United Kingdom
Phone: ++.44.207.594.9143
Fax: ++.44.207.823.7685
E-mail: Reda.Lebcir@ ic.ac.uk
Abstract: The current paper investigates whether the shift to more integration, that is use of
concurrent engineering process and cross-functional teams organisation, in new product
development (NPD) projects is suitable for all types of projects regardless of their level of
“project complexity”.
The current paper addresses this research question in two steps. First, a formal framework
of “project complexity” is developed for NPD projects in which its contributing factors are
determined. Second, a System Dynamics (SD) model is developed to investigate this issue.
The model is used to quantify the extent of “project complexity” effects on the relationship
between the level of integration in a project and one performance indicator: development
cycle time. The model was run for a single phase situation and showed that product
complexity and project uncertainty increases project development cycle time and that
increasing co-ordination does not offset these negative effects on project schedule
performance.
Key Words: New Product Development, Concurrent Engineering, Project Management,
Project Complexity, Product Complexity, Product Newness, Uncertainty, System
Dynamics.
Introduction
The business environment has changed dramatically in the last two decades creating new
challenges for firms in most industries. It has become more global, turbulent, and dynamic
making it difficult for firms to respond adequately to the shifting needs of markets and
customers. In this context, the development of new products is becoming increasingly
central to any strategy for achieving high levels of profitability, market share and, in the
long run, gaining a significant leverage of competitive advantage (Ulrich and Eppinger
1999, Wind and Mahajan 1997, Wheelwright and Clark 1992, Clark and Fujimoto 1991,
Gupta and Wilemon 1990).
However, developing such new products is a daunting task. Rapid changes in customers’
needs have shrunken products life cycle. Similarly, rapid technological changes are making
technical processes used to develop new products obsolete more quickly. As a
consequence, a bleak image is emerging regarding the performance of new product
development (NPD) projects. Research results show that failure is the rule rather than the
exception. For example, a significant fraction of new software and computer systems have
been marked by cost overruns, late deliveries, poor reliability and users’ dissatisfaction
(Abdelhamid and Madnick 1991). In other studies, Rodriguez and Bowers (1996) and Page
(1993) reported that most of NPD projects registered cost-overruns of 40% to 200% while
about 48% of resources are put on projects which are either cancelled before market
introduction or fail to yield suitable financial returns
One of the important reasons to explain these failures is the inadequacy of project
management procedures used to carry out these innovation projects (Langerak et al 1999,
Milson et al 1992). Developers’ technical abilities alone have not immune organisations
from witnessing the considerable rate of failure mentioned earlier. Project management is
the area, which should become the focus of attention if project performance is to be
improved. As pointed out by Abdelhamid and Madnick (1991) “the major breakthroughs
are now to be made in the management arena”.
Project management improvement has become more crucial as companies are facing new
challenges to carry out innovation projects. In response to the business environment
pressures cited earlier, most firms have re-engineered their NPD project management
paradigms from a sequential functional process to a concurrent cross-functional one.
Whereas this shift has increased dramatically the dynamic complexity of projects (Ford and
Sterman 1998, Rodriguez and Bowers 1996, Ford 1995), the mental models and decision
heuristics used by project managers have improved a little to deal with this increased
complexity (Diehl and Sterman 1995, Sterman 1994,1992).
1. Evolution of new product development project management paradigms
The traditional process, called the Phased Program Planning (PPP), was the first formal
process used to manage NPD projects. Its structure stipulates that the project should pass
by checkpoints sequentially to ensure that all the items required at a checkpoint are in good
order before the project moves sequentially to the next one (Wheelwright and Clark 1992,
Clark and Fujimoto 1991, Smith and Reinertsen 1991), Each phase of the project is
performed entirely within a specialised functional structure and the outcomes of the phase
are transferred in one “batch” to the subsequent one.
To help in the control of work evolution in such projects, many formal project management
techniques, based on network analysis, have been developed. The most famous are Critical
Path Method (CPM) and Project Review and Control Techniques (PERT) (Dreger 1992,
Moder at al 1983). These techniques are methods for planning, scheduling and controlling
projects. They aim to determine the activities which may constitute possible bottlenecks to
the progress of projects, help managers determine possible slacks and schedule slippage
available in some activities and how trade-offs between project schedule performance and
resources can be made (Dreger 1992, Moder at al 1983). The use of CPM/PERT methods
was suitable for the management of NPD projects under the old paradigm because they fit
well with their underlying assumptions. The development work is sequential. No
downstream task can start until all the dependent upstream ones are finished. Blocks of
development tasks were represented by activities in the CPM/PERT project network and
the precedence relationships were customised to represent the sequential dependencies
between development phases.
Despite their usefulness, CPM/PERT suffer from some limitations. Their underlying
assumption is that the work in the project will unfold as planned and no changes to its state
will occur until the project is finished. The precedence relationships between tasks imply
that when a task is finished, there is no possibility that a work can be done again on that
task. In addition, CPM/PERT do not address adequately the dynamic interaction between
the work structure, that is the map of tasks and their dependencies, and the human
environment. Factors such as fatigue, bumout, motivation, and experience, as important as
they are, are ignored in these methods.
The new project management process involves a more parallel execution of development
phases, a technique known as concurrent engineering (CE), and a cross-functional team
organisational structure (Swink et al 1996, Brown and Einsenhardt 1995 Zirger and Hartely
1994, Milson et al 1992, Gupta and Wilemon 1990, Takeuchi and Nonaka 1986). CE
includes overlapping activities in product and process development (Swink 1998, Swink et
al 1996, Hull et al 1996), simultaneous development of different product components and
sub-systems (Liker et al 1999), and integration of decisions regarding product design and
manufacturing capabilities (Liker et al 1999, Gerwin and Susman 1996).
The use of CE proved to generate many benefits for companies adopting it in their NPD
projects. Merits of CE include greater speed of development execution, increased
flexibility in product and process design, enhancement of shared responsibility and co-
operation, and stimulation of developers involvement in the project (Swink 1998, Takeuchi
and Nonaka 1986). However, the benefits associated with using CE are not priceless.
Successful implementation of CE has been found to be problematic in many organisations.
Adopting CE means changes in the nature and frequency of information flows between
developers, timing of upstream and downstream tasks, and the altitude throughout the
organisations towards dealing with uncertain and incomplete information (Krishnan et al
1997, Hauptman and Hirji 1996). As a result, CE has dramatically amplified the dynamic
characteristics of projects.
Scheduling and organisation of development tasks in CE contexts were at the origin of the
development of a methodology called the Design Structure Matrix (DSM) (Steward 1981).
The DSM matrix is based upon the analysis of the logical dependencies between
development tasks. This dependency is conceptualised through the information
requirements for each task as the previous ones are executed and their output information
becomes available. To organise the development work, partition algorithms are used to
find the best possible tasks execution sequence. Once the matrix is reorganised, it will
indicate the tasks which are sequential, parallel, and those which are coupled, that is the
tasks which depends reciprocally on each other to proceed, and, therefore, need to be
performed through iterations. However, even if DSM is a useful method to organise task
iterations in NPD projects, it remains a static method. Dependencies between tasks and
phases are assumed to remain stable over the project life cycle and, consequently, it is not
useful to describe the behaviour of a project over time.
Krishnan (1996) and Krishnan et al (1997) developed a formal mathematical model to
study the optimal overlapping strategy in sequential concurrent development activities. The
model stipulates that when overlapping occurs, the information released from upstream to
downstream is not in its final form but it is still being refined. As this refinement process
takes place, downstream phase starts its development work with the initial imperfect
information and accommodates the consequences of any changes in the information
released from upstream through development work iterations. The model represents the
refinement of information in the upstream phase and the amount of development work
necessary in the downstream phase to accommodate changes in upstream information
through the evolution and sensitivity concepts respectively. These concepts are used in a
mathematical program to decide about the optimal number of downstream iterations to
perform, the starting time of these iterations, and the time at which upstream information
should be finalised. The objective function is to minimise the total development cycle time.
The problem with this method is that it assumes a one-way directional flow of information
and does not indicate which factors affect the evolution and sensitivity concepts in the
project.
The adoption of CE was associated with a move from functional organisation to multi-
functional teams (Wind and Mahajan 1997, Gerwin and Susman 1996, Carmel 1995, Trygg
1993, Henke et al 1993, Wheelwright and Clark 1992). Two reasons triggered this
organisational switch. First, it is well established that NPD projects are inherently multi-
functional tasks. The second reason is that in CE environment, development work is
carried out simultaneously on different aspects of the product such as concept generation,
product design, process design, prototype building, and product testing. As a result, it is
necessary to have representatives from different functions to ensure shared control and
responsibility of the development work as phases are overlapped (Swink 1998, Swink et al
1996, Henke et al 1993). In fact as stated by Cooper (1994), “the nature of activities
(overlapped) virtually forces the use of cross-functional project team approach”.
2. Effect of project complexity on NPD project performance
Thus far, we described the operational process and the organisational structure dominating
NPD project management under the old and new paradigms. However, it is important to
indicate that before the NPD project actually starts, developers and management have to
make important decisions regarding the shape and destination of the product to be
developed. These decisions include product definition, the number of functions to be
performed by the product, the parts and sub-systems to be included, the breadth of the new
technologies to be included in the product, the amount of redesign to be performed on the
parts, and the market segment to be targeted by the new product. (Tatikonda and Rosenthal
2000a,b, Tatikonda 1999, Griffin 1997 ab, Olson et al 1995, Zirger and Hartely 1994,
Clark and Fujimoto 1991). These choices, which incorporate the new product “strategic
choices”, are important because they have several consequences over the NPD project life
cycle and beyond. (Griffin 1997 a,b,Wheelwright and Clark 1992, Clark and Fujimoto
1991, Smith and Reinertsen 1991)
Projects involving high innovativeness, different interacting new technologies, many inter-
related parts and sub-systems, a high fraction of newly designed parts, and directed to a
poorly understood market are obviously more difficult to manage and carry high levels of
risks (Tatikonda and Montoya-Weiss 2001, Griffin 1997 ab, Swink et al 1996, Iansiti
1995a,b,c). Non-familiarity with customer needs and requirements, product and process
technologies, coupled with a lack of information on how to proceed with development
work, diminish developers capability and confidence in executing the project work. One
project manager reported in Tatikonda and Rosenthal (2000b) describes well this situation
when he said
“Of course, we know what the big pieces are, but the problem is that we don’t know what the small
tasks are until we get there in the project, and oftentimes, these small tasks tum out to be big tasks”.
The first remedy to more effective handling of strategic issues in NPD projects is to
recognise that projects are not all similar and, consequently, they require different
managerial approaches. This argument is made even clearer by Tatikonda (1999), who
studied two different categories of NPD projects with respect to project complexity, the so-
called platform and derivative projects, and reported that.
[Platform and derivative projects represent different types of product development projects.
Different types of projects can have fundamentally different characteristics and, in tun, may require different
product development project planning and execution approaches. This is, a one shot, singular project
management approach may not be appropriate for each product in the family series. Use of a similar
approach may lead to reduced overall product development effectiveness ]
Unfortunately, firms still carry out projects with significant differences in project
complexity levels in the same way. Meyer at al (1997) found that “firms make little if any
explicit differentiation between more fundamental platform effort and the development of
derivative products”. Similarly, Shenhar (1998) indicates that there is no distinction, in
practice, among different types of projects in terms of project complexity. This situation
prevails even within the academic community as it was well described by Pinto and Covin
(1989):
“The prevailing tendency among the majority of academics has been to characterise all projects as
fundamentally similar.... The implicit view of many academics could be represented by the axiom: “a project
is a project is a project”.
In this context, the target of the current paper is to shed more light on this issue and
investigate whether the new NPD project management paradigms are suitable for all
projects regardless of their project complexity level.
This issue warrant more attention as the empirical results so far show no-conclusive, indeed
contradictory, results. For example, in some studies the use of cross-functional teams was
found to reduce cycle time for highly innovative projects (Liker et al 1999, Griffin 1997a,b,
Olson et al 1995). Other studies reported that their use had no effect on development time
regardless of the level of innovation in the project (Tatikonda and Rosenthal 2000b, Hull et
al 1996, Larson and Gobelli 1989). Similraly, CE was found to have a positive impact on
highly innovative projects (Swink 2000, Detoni et al 1999, Hanfield 1994). But, others
reported completely opposite conclusions (Swink et al 1996, Einsenhardt and Tabrizi
1995). Similar conflicting conclusions have been drawn regarding the effects of this
interaction on project quality and costs (Swink 1999,2000, Hull et al 1996, Larson and
Gobelli 1989). In summary, it is far from clear how the interaction between strategic and
operational characteristics in NPD projects affects their performance.
3. Definition of project complexity
Many project managers are using the term “complex projects” in describing the projects
they manage, yet it is not clear what are the factors contributing to this complexity. It is
until recently that a review within the project management literature has shed more light on
this issue (Williams 1997,1999a).
The first factor contributing to project complexity is related to the underlying structure of
the project and known as “structural complexity”. This factor was introduced by Baccarini
(1996) who defined project complexity, in a broader sense, as “consisting of many varied
interrelated parts’. This factor was breakdown into two dimensions. The first is
differentiation, that is the number of varied components in the project (tasks, specialists,
sub-systems, parts). The second is interdependence or connectivity, that is the degree of
inter-linkages between these components.
However, “structural complexity” does not account for the level of difficulty to carry out
project’s tasks. Williams (1997,1999a) argues that this “difficulty” is, in fact, the second
factor contributing to project complexity and define it as “uncertainty”. This factor means
that, contrary to the widespread belief, project goals and execution methods are not always
known and well defined at the beginning of the project execution (Tumer and Cohrane
1993). In many projects, a great deal of uncertainty about project’s goals and execution
methods remains after the project work has been underway. This uncertainty causes the
project work to become difficult and its outcome unpredictable, hence increasing the
overall level of project complexity.
The “uncertainty” factor has been also broken down into two dimensions: uncertainty in
methods and uncertainty in goals. Uncertainty in methods refers to the lack of knowledge
on how to proceed to achieve project goals. It represents situations in which the tasks to be
performed and the ways to perform them are not well known and defined at the beginning
of the project execution. This increases project complexity because the managerial
elements of the project in the form of project breakdown structures cannot be defined with
certainty. Uncertainty in goals refers to situations in which the project targets are ill-
defined at the beginning of the project This adds to project complexity because as the work
proceeds, requirements will have to be changed and refined many times causing changes in
the product components, layout, interfaces and architecture. In such situations, the basic
project management activities such as planning, scheduling, monitoring, and control
becomes ineffective as the structure of the product to be developed keeps changing over the
project life cycle.
4, The New Product Development perspective of project complexity
NPD projects are inherently complex because they involve development of products which
carry some degree of novelty. However, if there is an implicit acknowledgement among
practitioners and academics that NPD projects are complex, there is a great deal of
confusion about the drivers of this complexity (Ulrich and Eppinger 1999, Wheelwright
and Clark 1992, Smith and Reinertsen 1991, Clark and Fujimoto 1991). Thus far, there has
not been a single comprehensive framework which includes and integrate all the aspects of
project complexity in the context of NPD projects. Much attention has been devoted to the
technological novelty factor. The “structural complexity” factor, as important as it is, has
been relegated to a secondary level of importance (Tatikonda and Rosenthal 2001a, Swink
et al 1996, Ulrich 1995, Griffin 1997a,b, Zirger and Hartley 1994,1996)
The first factor contributing to project complexity in NPD projects is the level of “product
complexity”. The effects of product complexity on overall project complexity were first
highlighted by Clark and Fujimoto (1991) observed that if a new product contains many
interrelated parts, it becomes problematic to fit them together in a coherent whole.
Similarly, if a product consists of many parts, the number of possible interface
combinations between them increases exponentially (Murmann 1994). These studies
recognised implicitly that product complexity, in terms of the number of parts in the
product (differentiation) and their inter-linkages (interconnectivity), is a powerful driver of
overall project complexity. This definition of “product complexity" is, in fact, similar to the
concept of “structural complexity” described by Baccarini (1993) and Williams
(1997,1999a) within the project management literature.
The second factor driving “project complexity” in NPD projects is related to their degree of
“innovation” (see figure 1). “Innovation” may originate from new designs incorporated in
the product, new product technologies which improve the translation of customer
requirements into design parameters, or a new process technologies which ensure
compatibility between design specifications and process capabilities (Swink 1999, Souder
and Moneart 1992).
The “innovation” factor can be broken down into two dimensions: “product newness” and
“project uncertainty”. “Product newness” is defined as the portion of the new product
which has to be redesigned from previous generations of the same product (Griffin 1997
a,b, Wheelwright and Clark 1992). Product newness affects project complexity because if
its level of important, it will lead to an exponential increase in the number of tasks to be
performed to finish the project (Griffin1997a, Clark and Fujimoto 1991, Clark 1989).
Significant problems of interfaces and fitness between the new parts are likely to arise
leading developers to consider more design possibilities and alternatives (Swink 1999).
High levels of product newness require also important amounts of knowledge creation,
transfer, and synthesis (Zirger and Hartley 1994). Such projects are associated with an
intensive use of highly skilled labour, market knowledge, process ability, and considerable
transfer of information among the organisation (McDermott 1999).
The second dimension of innovation is “project uncertainty”. This dimension is inherent in
NPD projects since each project includes a certain jump into the unknown. The suitable
means, methods, and capabilities to be deployed in a project are rarely known to at the start
of the NPD project execution phase.
“Project uncertainty” occurs whenever there is a gap between “ the amount of information
required to perform the task (in this case the NPD project) and the amount of information
already possessed by the organisation (in this case the development team)” (Galbraith
1977). “Project uncertainty” includes many categories such as market, technological, and
resource uncertainties. Market uncertainty indicates the uncertainty about the market
segment targeted by the new product, and the definition and articulation of customers’
needs (Tatikonda and Montoya-Weiss 2001, Souder et al 1998, Olson et al 1995, Souder
and Moneart 1992). Technological uncertainty relates to the uncertainty about the best
technologies to be used in the product and/or process, and the degree of familiarity of the
team with the technologies involved in the project (Swink 2000, Tatikonda and Rosenthal
2000 a,b, McDermott 1999, Souder et al 1998, Swink et al 1996, Adler 1995, Olson et al
1995, Souder and Moneart 1992). Resources uncertainty reflects the uncertainty about the
quantity, quality, and mix of resources to be put in the project (Swink et al 1996, Souder
and Moneart 1992). Project uncertainty increases the level of “project complexity” because
the wider is the gap between the required information to perform the project and the
available information within the organisation, more it becomes difficult and lengthy to
perform project tasks as the leaming curve is slow, problems solving methods inaccurate,
and the set of possible solutions large. Prior experience is not very helpful in these
situations because developers face new challenges which they have never tackled before
(Olson et al 1995).
5. The NPD Project System Dynamics Model
The model focuses on the description of development process of a single project although,
in practice, the dynamics observed within a project is linked to the dynamics of a portfolio
of projects. However, a clear understanding of multi-project dynamics cannot be achieved
unless the issues involved in single projects are deeply investigated. It is assumed that the
organisational structures and the technological capabilities are defined at the beginning of
the project and will not change over the project life cycle. Organisational stability ensures
that co-ordination mechanisms, planning and monitoring procedures, decision-making
tules, and relationships between developers and project management are defined and
cleared at the beginning of the project. The technology to be used in the project is available
at its starting point and developers are not offered the luxury of incorporating newer
Project Complexity
v u
Product Complexity Innovation
Product Scope Product Product Project
-Number of Architecture Newness Uncertainty
Parts. -Parts -Extent of -Technological
-Number of Interdependence Product Change -Market
Functions -Technologies -Portion to be -Resources
Interaction Redesigned
Figure 1: Project complexity factors in new product development projects
technologies once the project get underway (Gupta and Wilemon 1990). This assumption
is important because many technologies related parameters in the model such as average
activities duration, average delays in human resource management, and reference values for
developers effectiveness are assumed constant in the model.
The project is divided into phases. A phase is a sub-structure of the project which
accommodates similar set of activities (Cooper 1994). The conceptualisation of NPD
projects as multi-phase processes is important within the context of this research. It enables
to determine the boundaries between different project phases and to draw the line between
the internal and external influences on a project phase.
To model the development project progress, it is assumed that each phase consists on a
certain amount of “development tasks”. When these tasks are performed, they generate the
information which constitute the output of the development phase. In the current research,
a development task is defined as “an atomic unit of development work” (Ford and Sterman
1998, Ford 1995). It is important to emphasise that the selection of “development tasks” in
a project is phase related. For example, if the model focuses on a new car development
project, “development tasks” in the product definition phase of the project would be the set
of product concepts and specification for each part of the car. However, development tasks
for the product design of the same project would be the set of dimensions and geometrical
forms of the car components. Development tasks are important because they represent the
unit of measure for project progress. In the current model, project progress is measured by
the fraction of “development tasks” released from the development phase. They also serve
as the base of many decisions in the project. For example, information about the number of
“tasks completed”, “tasks in rework”, “tasks remaining”, and “tasks waiting approval” are
triggers of most decisions regarding human resource hiring and allocation, project targets
alteration, co-ordination mechanisms, integration levels, and so on.
The last assumption in the model is related to the “project complexity” level in the project.
As described earlier, project complexity consists of three factors: product complexity,
product newness, and project uncertainty. The assumption here is that these three factors
have a fixed level for a given project (Tatikonda and Rosenthal 2000a, Griffin 1997a). The
reason is that in a project, the level of “project complexity” is set by strategic choices taken
prior to the start of the development work. Such choices cannot be subject to alteration
once the project work gets underway.
The framework on which the SD model presented in this research is grounded combines
elements drawn from NDP theoretical frameworks briefly described earlier and from
previous SD models. Theoretical frameworks provide the main variables and concepts
affecting NPD performance whereas SD models provide some of the established inner
feedback structures which link some of the variables found to be pertinent with respect to
project performance. A review of the NPD theoretical frameworks and previous SD
models indicates that NPD project performance is affected by the following:
¢ Development process structure: This includes the different development activities
involved in a project, the level of concurrency among phases, and the structure of
the development work within each phase.
¢ Resources and team characteristics: This represents the level and mix of resources
committed to the project, the level of developers experience and training, the
number of projects each developer is involved in, the proportion of full and part
time developers in the project, and developers effectiveness in executing
development tasks.
¢ Tasks Characteristics: This deals with the qualitative issues regarding development
tasks. It includes the level of tasks difficulty perceived by developers, the amount
of information available to carry out development tasks, and the proportion of new
tasks in the project.
¢ Project size: This indicates the number of tasks needed to execute the project, the
amount of rework due to errors, and the work to be added to the project due to
initial underestimation of the real project size.
¢ Project objectives: This includes the setting of the initial project targets in terms of
development cycle time, project cost, and project quality. It also determine the
mechanisms to alter project goals, that is the project management level at which the
decisions about project targets revisions are made (development team, project
manager, or senior management), and the power hold by the team relatively to
senior management.
* Top management support: This represents the interaction between senior
management and project development team. It includes the priority given to the
project in terms of getting resources, the effects of senior managers’ support on
developer productivity, and the decision mechanisms related to goal alteration.
In the simulation model, each phase of the development project is represented by the
generic structure presented in figure 2. In this structure, project performance in each phase
is effected by the interaction of development process structure, project resources, project
tasks characteristics, project size, project objectives, and the level of top management
support. Development process simulates the different activities involved in the project, the
nature of concurrency relationships among development phases, internal progress structures
imposed by information and physical availability of work within the phase, and the
generation, inheritance, and correction of errors and changes. Resources simulates the
hiring and training of personnel, allocation of personnel labour among development
activities, fluctuations of developers productivity in response to project conditions, learning
and experience accumulation, and overtime work. Tasks characteristics simulates the
effects of task difficulty and the fraction of new tasks in the project. Project size simulates
the effects of changes to initial phase scope (number of tasks), the effects of rework, and
the mechanisms of late work discovery and inclusion in the project. Top management
support simulates the effects of senior management involvement in project objective
alteration, approval of engineering changes and priority given to the project. Objectives
simulate the level of initial goals and how they are changed in response to project
conditions.
The project complexity factors (that is product complexity, product newness, and project
uncertainty) interact with the previous operational characteristics to drive phase
performance. Product complexity, which is the parameter indicating the number of tasks
and their interdependence, affects development process, resources, and tasks
characteristics. Product newness, which is the fraction of new tasks in the development
project, affects development process, task characteristics, resources, and top management
support. Project uncertainty, which represents information gaps and risks due to market,
technical, environmental, and resource uncertainty have effects which span over all the
operational characteristics in the project phase.
Because the model represents a multi-phase project, the interactions between operational
characteristics and project complexity factors have ramifications at two levels. The phase
level, which focuses on management practices taking place within a single phase of the
project (intra-phase level), and project level, which focuses on those practices governing
the interaction among different phases (inter phase level). These interactions are described
in the following:
Intra-phase level
A phase includes planning and execution. Development work execution does not start
until sufficient information about the methods to carry out the tasks is released from the
planning process.
Some tasks cannot be planned until the phase has registered a certain progress in its
work. Such tasks remain in planning until enough information from work execution is
available.
Development work execution is constrained by task planning information and task
physical execution availability.
Once a task is completed, it undergoes a testing procedure. If the tests are satisfactory,
the task is approved. Otherwise, the task will have to be reworked.
Once the tasks are approved, they are not released immediately to downstream phase.
They are hold within the phase until there is sufficient information to be released.
Changes occurring later in the phase may make some of the work already done and
approved redundant. In such cases, some of the finished work will have to be done
again.
The extra rework due to late changes in a phase will have to be approved by project
managers and co-ordinated with other developers before it is reworked.
Each time a task is reworked, it undertakes the testing procedure before it is approved
and released again.
Decisions about human resource management are made within the phase according to
the status of the project. The status is determined by the level of discrepancy between
the phase real and planned targets.
Inter-phase level
Development work released from an upstream phase to its downstream dependent ones
determines the availability of work in downstream phase.
Changes which escape testing procedures in an upstream phase are released to
downstream phases and corrupt the work within these phases.
If a downstream phase discover an inherited change form upstream phases, it return it to
the phase which generate the change. The change is co-ordinated before it is worked
again.
Released tasks, which become redundant as a result of tasks interconnections, are
recalled from downstream phases and co-ordinated before being reworked.
The simulation sectors presented in this paper are related to the development process
structure part of the model. The feedback loops representing this part of the model are
shown in figure3. The detailed description of the stock and flow structures (Sterman 2000,
Richardson and Pugh 1981, Forrester 1961) of the development process is presented in the
next section. It includes the planning sector and the development sector.
p| Project Performance lq
-Development Time
> -Project Cost
gl -Defect Rate a
Development Process Resources
-Development -Quantity / Effectiveness
Activities -Allocation Among
-Phase Dependency Product Activities / Training
Complexity -Fraction of Time to
Project
Tasks Characteristics Top Management Support
-Task Difficulty -Project Priority
-Proportion of new tasks -Goals Alteration
-Project review
Project Size Objectives
-Number of Tasks -Schedule
-Rework -Budget
-Late work discovery Newness -Quality Goal
Figure 2: Generic Structure for Each NPD project phase
5.1 The Planning sector
This sector simulates planning activities, that is the activities taking place before the actual
development execution starts. Planning activities are important because they set the
framework within which the development execution will take place (Iansiti 1995 c).
Effective project planning phase improves developers problem solving capabilities and
identify potential sources of problems early in the project (Thomke and Fujimoto 2000,
Khurana and Rosenthal 1998). The outcome of the project planning phase is a set of
product requirements, project objectives, technology choices (Tatikonda and Rosenthal
2000 a), design and manufacturing capabilities, skills, procedures, and project structures
(Adler 1995)
‘G)
Rework to «Rework to
G) coordinbte + aoe
Tasks fraction'n 4
rework Frat
changed
+ G)
Extra rework due to
Gh Gate rate product complexity
ca +
Quality en Task approval rate
Tasks available for
planning a
+ NN completed Product
not checked. . complexity
pe Tasks a
Tasks to plan
o @
a 7 ltion rate é
Total fraction i
completed
= r _ to os 4)
a
Planning rate Completion intemal
concumency
Tasks available for a8
completion _+ Tasks fraction
——+_______ perveived satisfactory
‘B4 Delay \\
Qa
Pret st size
adjustment rate
Project uncertainty
wu
Figure 3: The feedback structure for the development process
The stock and flow diagram which simulates the project planning process is presented in
figure 4. The stock of tasks to be planned Trp whose initial value is equal to the phase
scope (number of development tasks in the development phase), is depleted at a certain rate
per unit time determined by the planning rate:
d/dt (Trp) =-a (1)
The planning rate (a) is determined by the minimum value allowed by the planning
development structure process (the number of tasks available for planning at any given
time) and the planning labour which represents the availability of labour to perform the
planning activities.
The Planning Sector wx 8
Scope
= i
Intemal planning concurrency
Total Tasks avaijable for plannin:
lanning Process li
Tasis still to be planned
Average Planning Duration
Tasks to plan Tasks planned planning release rate
Planning Labour Limi
planning release time
T fis adiftion rate
Fraction of fasts planged Planning Fraction Lower Limit
Scope
Planning Release time
Scope Adjustment Rate
Figure 4: The planning sector stock and flow diagram
a= Min (Pp, Pia) (2)
Pp is equal to the tasks still to be planned (Tsp) divided by the average planning duration
(1).
Ppi=Tsp/ B (3)
The variable Tsp has been taken here instead of the stock of tasks to plan Typ because at the
beginning of the development phase, not all tasks can be planned. It is virtually impossible
to specify all tasks completely before project execution begins (Iansiti 1995c). Information
on how to proceed to plan some tasks may not be available until late into the development
phase. This characteristic of the planning activity is known as the “isolation and
absorption” principle (Laufer et al 1996). In some situations, it is necessary to isolate some
tasks which are impossible to plan at the phase start, plan and execute other tasks in the
meantime, and then use the generated information by the development execution process to
plan the isolated tasks.
In this context, at any given time, the total number tasks available for planning (TT,p) is
not equal to the phase scope S, but to a fraction of it. The value of TT ap is equal to:
TTap=S x Pec (4)
Planning concurrency Pcc is a non-linear function, which represents the fraction of tasks
available for planning with respect to the fraction of tasks which has been already
completed at least once. The latter fraction is equal to the fraction of tasks perceived
satisfactory (Frps) and the fraction of tasks in rework (Frr) (the variables Frps and Fre will
be described in more details in the process development sector). Therefore:
Pec =f (Fres + Frew) (5)
The number of tasks still to be planned Tsp is equal to the total tasks available for planning
TTap minus the number of tasks which have been already planned. The latter number of
tasks is equal to the difference between the phase scope S and the stock of tasks to be
planned Trp, This lead to the following equation:
Tsp = Max (0, TTap-(S- Trp) (6)
The tasks which have been planned are not released immediately for completion. The
information generated by the planning process is kept for a while until a sufficient amount
is accumulated to allow a smooth starting of the tasks completion process. Between the
instants that tasks are planned and released fore completion, tasks are accumulated in a
stock of tasks planned Tp.4n, This stock change over time at the following rate:
d/dt (Tpian) =a-b (7)
The planning release rate depends on how much of the tasks have been already planned.
To ensure that planned tasks are not released immediately, a minimum fraction of tasks has
to be planned. Once this threshold value is reached, planning information starts to flow to
development execution. The threshold value is set in the model through the parameter
lower planning limit Lpyimrr which is chosen in practice by the modeller. Therefore:
b=Tpran/ Bircr If FTpran2=Leiumir — (8)
Otherwise
The fraction of tasks planned is given by the number of tasks planned to date divided by the
phase scope. The number of tasks already planned is equal to the phase scope minus the
stock of tasks to plan (Equation 6). Consequently, the fraction FTp.an is given by the
equation:
FTpran = (S- Trp) /S (9)
5.2. The Development Sector
This sector simulates the development process within a development phase. It includes the
mechanisms which alter development tasks states after tasks have undertaken a planning
phase. In the current model, each possible state of a development task is represented by a
stock. The movement of tasks among stocks (states) is dictated by the rates at which the
development activities are performed. The stock and flow diagram representing the
development sector is shown in figure 5.
The development sector includes four stocks which determine the completion and release of
development tasks. These stocks are “Tasks to complete Trc”, “Tasks completed not
checked Teno”, “Tasks approved Ta ppry”, and “Tasks released Tretease”.
The tasks to complete stock Trc receives the tasks moving from the tasks planned stock
Tpran. Once the threshold planning fraction Lpiuimir is reached, tasks starts to move to the
stock of tasks to complete Tr¢ signalling the start of the development execution phase.
Tasks are executed and move to the stock of tasks completed not checked Tcnc. The rate in
which the tasks move between these two stocks is dictated by the base-work activity. Base-
work activity is defined as the execution of a development task for the first time.
Once a task is completed for the first time, it undertakes a verification process to make sure
that it is not flawed. If the task pass this checkpoint successfully, it is approved.
Otherwise, the task will have to be corrected (reworked) another time to address the flaw
found in the task. From a stock and flow perspective, this means that there are two
outflows from the stock of tasks completed not checked Tcnc. The first outflow moves
tasks to the stock of approved tasks T,ppry. The second outflow moves tasks to the stock
of tasks to be reworked Treworx. The rate of these two outflows is determined by the
quality assurance (QA) activity, which represents the verification process occurring within
a development phase. The tasks which move to the stock of tasks to be reworked Trework
move again to the stock of tasks completed not checked Tcnc where they are checked again
for possible flaws. The rate at which the tasks move from the former to the latter stock is
determined by the rework activity, which indicates the work carried out on a task for
correction purposes.
The tasks found correct after the quality assurance activity are hold in the stock of tasks
approved Tppry until they are released to subsequent phases. This process is represented
by the movement of tasks from the stock of approved tasks T,ppry to the stock of tasks
released Trerzase. Task release means that the information generated through development
work within a phase is transferred to the subsequent phases. For example, tasks released
from a product definition phase in a new car development project would be a set of the
car’s parts specifications.
The equations which represent the previous stock changes over time are in the following:
d/dt Trc= b-c (10)
d/dt Toncu =c+g-d-e (11)
d/dt Tappry =e-f-h (12)
d/dt Trevease =f (13)
The base-work completion rate c is equal to the minimum value between the base-work
process limit and the base-work labour limit. The base-work process limit, which is the
rate of base-work completion allowed by the process structure, depends on base-work
availability. In this context, base-work availability BSW ay is the minimum value between
the base-work available due to concurrency BAVcc and base-work available due to
planning BAVp..
BSWay =Min (BAV¢c, BAVp) (14)
The value of BAVp, represents the information constraints put on the availability of
development work due to lack of tasks released from the planning activity. BAVcc
represents the physical constraints put on the availability of the current work given the
work already done. The latter constraint is similar the internal gates presented in previous
SD models (Notzon 2000, Ford and Sterman 1998,1999, Ford 1995, Homer et al 1993). It
represents how much work is currently available given the work which has been already
finished.
The value of base-work available due to planning BAVpr is simply equal to the stock of
tasks to complete Trc. The value of BAVcc is much more complicated to determine. Ina
phase, not all the development work is available for completion once the planning stage is
finished. Some development work remains unavailable for completion unless some pre-
required tasks have been performed. For example, if a new car is being developed, the
design of some components cannot start until parameters and geometrical form of the car
body has been determined.
To model this type of constraints, we will use a base-work process concurrency BScc
function which determines the fraction of the phase scope S available for base-work
completion given the fraction of tasks perceived satisfactory Frps by developers. The latter
value is the total tasks perceived satisfactory TTps, which is equal to the sum of tasks
completed not checked Tcncu, tasks approved Tappry, and tasks released Tpevease.
Therefore, at any given time, the total tasks available for base-work completion TT pswe is
equal to the product of the phase scope S and the base-work process concurrency BScc.
oD The Proces Development Sector As
"Discover intra Phase rework foduct complexity
EPCRW
Extra Approv RW due to PC
Pit acwedcaua tbe appv Effect of PU on Pr Discover RW
b
Project uncertainty
in team approv time
Th team approv rate
O
Out team apprOktime|
16h discover rework Max Prob Discover Rework
Extra rework due to PC for inter coord
Prob Intra phase re
:
Out team approv rat
Inter Coord Labour Limit
Average QA Duration
intemal coordination rate i
Gon to be reworked
QA plocess limit
A LabourLimit
bb
Discover inva’Rhase refhork
Average Release duration
Average int Coord Duration,
A Rate
Rework Yabour Limit
Tasks aphwte Tasis released
Tasks compledfd not checked
a
Reworktass ate ‘Approved tasks rate Release rate
Average Rework Duration
res
Complgx6n avaialbility ra
Tass to complete
. BaseworkLabour Limit
Planning release rate Scope Tasks perceivel satisfactory
Basework process limit,
Average Basework Duration
Basework available due to planning
Basework available due to concurrency Fraction perceive} satistactory 2
‘Total Tasks Available for completion
= ase Basework Process concuntence
Tasks perceived satisfactory
Figure 5: The development sector stock and flow diagram
TTps=Toncu + Tapprvt TreLEase
Frps=TTps /S
BScc=f (Fres)
TTgswe=S X BScc
Total tasks available for base-work completion TTgswc includes the tasks which have been
already executed at least once and the tasks which are still to be completed. Therefore, the
number of tasks corresponding to base-work available due to concurrency BAV cc is equal
to the total tasks available for base-work completion TTgswc minus the tasks which have
already completed at least once. The latter number of tasks is equal to the phase scope S
minus the total tasks perceived satisfactory TTps and the total tasks in rework TTaw.
BAVcc= Max (0, TTsswe- (S-TTps-TTaw)) (19)
The maximum condition is put here to avoid situations when an important number of tasks
are still in planning phase. Such situation means that the values of TTps, TT pw, and
TTgswe are low and therefore BAVcc may become negative, a meaningless situation. In
practice, this reflects the situation when most of the tasks are still in planning and not
enough information is being released to start completion work and, therefore, physical
constraints on base-work evolution have not yet become effective.
As mentioned earlier, the activity associated with task verification is defined here as quality
assurance (QA). The rate at which this activity is carried out is determined by the
minimum value between the quality assurance process limit QA, and the quality assurance
labour limit QALL
QA =Min (QApt, QAtt) (20)
The quality assurance process limit QApz is equal to the stock of tasks completed not
checked Tencu divided by the average quality assurance duration Ta
QApi=Tencu/ Wa (21)
Once flawed tasks are discovered, they move from the stock of tasks completed not
checked Tencx to the stock of tasks to be reworked Treworx. The rate d at which tasks
move between these two stocks depends on the quality assurance rate QA and the fraction
of tasks which needs to be reworked FNreworx. The latter fraction is the product of the
probability that a task needs rework (task flawed) PNreworx and the effectiveness of
developers to detect flawed tasks. Developers' effectiveness to detect flawed tasks is
quantified through the probability of discovering a rework PRpsrework.
d= QA x FNrework (22)
FNrework=PNrework X PRosrework (23)
The tasks which are not detected to need a changed are approved and move from the stock
of tasks completed not checked Tcncu to the stock of tasks approved Tappry. The tasks
approval rate e is simply the quality assurance rate QA minus the rate at which changes are
discovered d.
e=QA-d (24)
The probability of discovering a rework PRosreworx is affected by the project uncertainty
level PU. Uncertainty means that there is insufficient information about the task, so
chances are high that a flawed task is considered correct and, therefore, is mistakenly
approved. Therefore, the probability of discovering a rework PRpsrework is equal to the
product of a maximal probability to discover a rework MAX PRosreworx and the effects of
project uncertainty EPUpsreworx. The latter effect is a non-linear function with respects to
project uncertainty PU.
PRopsrework = MAX PRopsrework X EPUpsrework (25)
EPUpsreworx =f (PU) (26)
The flawed tasks due to developers’ work errors are not the only tasks to be reworked. In
fact, product complexity PC, which is a parameter capturing the interconnections among
tasks, affects also the number of tasks to be reworked. One of the most important
consequences of tasks connectivity is that if some late tasks are found flawed, some other
tasks which have been previously approved and released will have to be reworked again.
This is the situation in which a change in a task, such as the design of a component,
generates more work than the original one(Williams 1999b).
The process of changes due to product complexity is modelled by the introduction of two
new stocks “Extra rework due to PC to approve RWexrapprov” and “Extra rework due to
PC for internal co-ordination RWextircoor’. Tasks which become redundant as a result
of product complexity will move form the stock of tasks approved Tappry to the stock of
Extra rework due to PC to approve RWextapprov. This approval is necessary because these
changes have not occurred because of developers mishandling of development work, but
due to task interconnections. These changes go generally through an approval stage before
they are reworked again (Loch and Terwiesch 1999, Williams 1999b). Once these changes
are given the “go-ahead” decision for rework, they will have to be co-ordinated within the
development phase before the actual rework takes place.
The movement of changes due to work made redundant as a result of product complexity is
determined by the following rates: approved rework rate due to product complexity h, in-
team approval rate k, out-team approval rate 1, and internal co-ordination rate m. The
changes over time of the stocks representing detection and correction of flawed tasks and
changes due to product complexity are:
d/dt Treworx= d+m-g (28)
d/dt RWexrapprov.=h-k-l (29)
d/dt RWextintcoor =k+l-m (30)
The rate h depends on the level of product complexity PC. The higher the value of this
parameter, the higher are the interconnections among tasks, and hence it is more likely that
a flawed task makes more already accomplished tasks redundant. This relationship is
captured by a non-linear function which determines the effect of product complexity on
rework EPCaw with respect to the parameter product complexity PC.
EPCaw =f (PC) (32)
The second parameter determining this rate is the discover rework rate d. In fact, redundant
tasks due to product complexity become so because they are linked to tasks which are being
found flawed through quality assurance activity. Therefore, rate h depends on the rate d.
More flawed tasks discovered, more interconnected tasks to them become redundant.
Consequently, the equation for h is
h= Max (0, FT appry x dx EPCpw) (33)
These tasks have to be approved by project managers before they are reworked. To model
this process, I used a quantification of team approval power similar to the one presented in
Zirger and Hartely (1996). They determined it as “the fraction of decisions outside the
team control”. This fraction is modelled here as a probability that a task needs an out-team
approval PRourream. Therefore, the rates of changes approval k and 1, that is in-team and
out-team approval rates respectively, are given by
k=(RWextapprov /twream) X (1- PRourream) (35)
1= (RWexrapprov /Tourream) X PRourream (36)
The average in-team approval duration twream is in fact equal to dt, the time unit, because a
change which does not require project management approval moves instantaneously to the
stock of extra rework due to PC for internal co-ordination RWextintcoor
Intemal co-ordination activity takes place to address integration concems between
developers working within the same development phase but on different components of the
product. Internal co-ordination takes place in high product complexity environments
because developers work generally on different product “sub-systems” and “components”
simultaneously (Clark and Fujimoto 1991)
The rate m at which this activity is performed is determined by the minimum value between
the intemal co-ordination process limit INCp,, and the internal co-ordination labour limit
INCit
m= Min (INCp1, INC) (37)
The internal co-ordination process limit INCp, is determined by the stock of extra rework
due to PC for internal co-ordination RWexrinrcoor and the average internal co-ordination
duration trcoorp-
INCp, = RWextintcoor / twrcoord (38)
Before the description of the development sector come to conclusion, it is necessary to
recall that in the planning sector described previously, two quantities have been mentioned
without explanations: Fraction of tasks perceived satisfactory Frps and fraction of tasks in
rework Fraw (Equation 5). Frps is presented in equation (16) above. Fraction of tasks in
rework Frpw is equal to the total tasks in rework TT pw, that is the number of tasks in
rework or waiting to be changed, divided by the phase scope S. The former value is equal
to the number of tasks in the stock of extra rework due to PC to approve RWextapprov,
extra rework due to PC for internal co-ordination RWextiwtcoor, and tasks to be reworked
TREWORK
Fraw=TTrw/5S (39)
TTaw=Treworx + RWextapprov +RWextintcoor (40)
Finally, activities duration depends on the level of innovation in the project. As described
earlier, innovation has two components: product newness PN and Project uncertainty PU.
The former refers to the size of change taking place in the new product whereas the latter
indicates the level of difficulty associated with these changes. Clearly, both parameters
influence activities duration time. A sizeable change will take longer because there are
more new tasks to perform as the number of alternatives to consider is important (Murmann
1994). A difficult task requires more time because of lack of information on how to
proceed with it (Emmanuelides 1993, Iansiti 1995b,c). Therefore the average activity
duration time is equal to the product of the minimum activity duration inacr and the
effects of product newness EPNrm and project uncertainty EPUrm. The two effects are
non-linear function depending on the product newness PN and project uncertainty PU
levels.
Tact = Minact X EPNrm x EPUrm (41)
EPNrm =f (PN) (42)
EPUrm =f (PU) (43)
ACT = Planning, base-work, quality assurance, rework, internal co-
ordination
6. Simulation results for single phase model
In order to get some early results, the single-phase simulation model was run to investigate
how the integration within a development phase affects its performance. Although, the
model generates the behaviour of three performance indicators: development cycle time,
project quality, and project cost, the discussion here is limited to the behaviour of the
development cycle time. Discussions related to the multi-phase model and other
performance indicators will be the subject of a separate paper. The parameters values used
in these runs are not from a real project, but from some of the previous SD models. Formal
parameterisation is being undertaken currently on a project within the Aerospace industry.
In the set of simulation runs described here, I analysed the effect of interaction between
two project complexity factors, that is product complexity (PC) and project uncertainty
(PU), and integration represented by the internal co-ordination activity. PC is assigned two
values: low and high whereas PU is assigned three values: low, reference, and high.
Integration is evaluated through two levels: low and high. Development cycle time is
represented by the time needed to release all the phase tasks. For each level of integration
and product complexity, a sensitivity analysis was conducted with respect to project
uncertainty. The behaviour over time of the variable “tasks released” is presented in graphs
1to 4.
The graphs show that development cycle time increases as the level of project uncertainty
goes up from low to high. This behaviour holds for both situations of low and high PC.
However, development cycle time increase is more dramatic when PU moves from its low
to reference value. The jump is not equally important when the value of PU moves from
reference to high value. This indicates that there is a decreasing marginal effect of PU on
the development cycle time. Although the effect of PU on cycle time is dramatic, once PU
reaches a certain level, its increasing effect is no longer strong. This shows that even
moderate levels of project uncertainty may have considerable effects on cycle time.
From the product complexity perspective, a similar picture is emerging. If PC increases
from low to high level, development cycle time increases for the three levels of PU. This
also indicates that PC is an important driver of development cycle time. However, in this
situation, the development cycle time increase is similar for the three levels of PU. This
support the view that firms should be careful when they decide about the architecture of the
new product to be developed, an aspect of project complexity which has been often
relegated to a secondary level of importance in NPD projects.
It appears also from the results that integration is not very helpful in compensating the
effects of project complexity. No significant improvement in performance has been made
when integration moves from low to high level. However, this may be understandable in
the single-phase model. Internal co-ordination is associated only with the redundant work
due to product complexity. I suspect that even if this activity is given a high priority, it
cannot offset the negative consequences of high PC and PU. This indicates that it may be
more beneficial to concentrate the efforts on other execution activities such as planning and
base-work to avoid generating errors in the first place. In any case, this is just a
preliminary analysis regarding the effects of integration. A more detailed and in-depth
analysis will be presented in a coming paper describing the multi-phase model.
BD 1: Tasks released
1
1900.004
950.00-4~
1.00
aea* ?
0.004 ruil
2: Tasks released
3: Tasks released
2. 2.
1 3 rT 1.
2
3
T
200.80 400.60 600.40 800.20 1000.00
Graph 1 (Untitled) Days 15:57 05 Apr 2002
Graph 1: Development cycle time (high integration, high product complexity)
BD 1: Tasks released
1
2: Tasks released
3: Tasks released
190.005 |
| 3
2, 2. 2.
950.004
| tI: 1 1
Vi
7 y
0.004 A
1.00 200.80 400.60 600.40 800.20 1000.00
a af 2 Graph 1 (Untited) Days 15:58 05 Apr 2002
Graph 2: Development cycle time (high integration, low product complexity)
BD 1 Tasks released 2: Tasks released 3: Tasks released
1: 1900.00.
| 2, 2.
As 1 1.
R
2
1 950.004
1
400.60 600.40 800.20 1000.0
OGEF PF Graph1 Untitea) Days 16:00 05 Apr 2002
Graph 3: Development cycle time (low integration, high product complexity)
BD 1-Tasks released 2: Tasks released 3: Tasks released
0 1900.004
3
v
- 2: 2:
i: 950.004
ri: 1. 1
U
1
L 0.004 4
1.00
200.80 400.60 600.40 800.20 1000.00
a BaF 2 Graph 1 (Untitled) Days 16:01 05 Apr 2002
Graph 4: Development cycle time (low integration, low product complexity)
References
Abdelhamid TK and Madnick S.1991. “Software project management dynamics: an
integrated approach”. Prentice Hall, New Jersey.
Adler PS.1995. “Interdepartmental interdependence and co-ordination: the case of the
design/manufacturing interface”. Organization Science, 6(2), 147-167.
Baccarini D. 1996. “The concept of project complexity-a review”. International Journal of
Project Management, 14(4), 201-204.
Brown SL and Eisenhardt KM.1995. “Product development: Pat research, present findings,
and future directions”. Academy of Management Review, 20(2), 343-378.
Carmel E.1995. “Cycle time in packaged software firms”. J ournal of Product Innovation
Management, 12(1), 1-14.
Clark KB.1989. “Project scope and project performance: The effect of part strategy and
supplier involvement on product development”. Management Science 35, 1247- 1263.
Clark KB and Fujimoto T.1991. “Product development performance: strategy,
organization and management in the world auto industry”. Harvard Business School
Press, Cambridge, MA.
Cooper RG.1994. “Perspective: Third generation new product process”. J ournal of Product
Innovation Management, 11, 3-14.
De Toni A, Nassimbeni G, and Tonchia S.1999. “Innovation in product development
within the electronics industry”. Technovation, 19, 71-80.
Diehl E and Sterman JD.1995. “Effects of feedback complexity on dynamic decision
making”. Organizational Behavior and Human Decision Processes, V 62(2), 198-215.
Dreger JB.1992. “Project management”. Van Nostrand Reinhold, New Y ork.
Emmanuelides PA.1993. “Towards an integrative framework of performance in product
development projects”. Journal of Engineering and Technology Management, 10
363-392.
Eisenhardt KM and Tabrizi B.1995. “Accelerating adaptive processes: product innovation
in the global computer industry”. Administrative Science Quarterly, 40, 84-110.
Ford ND.1995. “The dynamics of project management: an investigation of the impacts of
project process and co-ordination on performance”. Unpublished PhD thesis,
Massachusetts Institute of Technology, Cambridge, MA.
Ford ND and Sterman JD.1998. “Dynamic modelling of product development processes” .
System Dynamics Review 14(1), pp 31-68.
Ford ND and Sterman JD .1999.” Overcoming the 90% syndrome: Iteration management in
concurrent development projects”. Unpublished working paper, System dynamics group,
Sloan School of Management, Massachusetts Institute of Technology, Cambridge, MA.
Forrester JW (1961). “Industrial dynamics”, The MIT press, Cambridge, MA.
Galbraith JR (1977). “Organization Design”. Reading MA, Addison-Wesley
Gerwin D and Susman G.1996. “Special issue on concurrent engineering”. IEEE
Transactions on Engineering Management, 43(2), 118-123.
Griffin A.1997a. “The effects of project and process characteristics on product
development cycle time”. Journal of Marketing Research 34(1), 24-35.
Griffin A 1997b. “Modelling and measuring product development cycle time across
industries”. Journal of Engineering and Technology Management, 14, 1-24
Gupta AK and Wilemon DL 1990. “Accelerating the development of technology-based
new products”. California Management Review, Winter 1990, 24-44.
Hanfield RB.1994. “Effects of concurrent engineering on make to order
products” IEEE transactions on Engineering Management, 41, 384-393.
Hauptman O and Hirji KK.1996. “The Influence of process concurrency on project
outcomes in product development: An empirical study of cross-functional teams”. IEEE
Transactions on Engineering Management, 43(2), 153-164
Henke JW, Krachenberg RA and Lyons TF.1993. “Perspective: cross-functional teams,
good concept, poor implementation”. J ournal of Product Innovation Management 10
216-229.
Homer JB, Sterman JD, Greenwood B and Perkola M.1993. “Delivery time reduction in
pump and paper mill construction projects” Proceedings of the 1993 International System
Dynamics Conference, Cancun, Mexico. Monterey Institute of Technology.
Hull FM, Collins PD, and LikerJK.1996. “Composite forms of organisation as a strategy
for concurrent engineering effectiveness”. IEEE Transactions on engineering
Management, 43(2),133-142.
Tansiti M.1995a. “Science based product development: An empirical study of the
mainframe computer industry”. Production and Operations Management, 4
353-59.
Iansiti M.1995b. “Technology development and integration: An empirical study of the
interaction between applied science and product development”. IEEE Transactions on
Engineering Management, 42(3), 259-269.
Tansiti M.1995c. “Technology integration: Managing technological evolution in a complex
environment”. Research Policy, 24, 521-542.
Khurana A and Rosenthal SR.1998. “Towards holistic “Front Ends” in new product
development”. Journal of Product Innovation Management, 15, 57-74.
Krishnan V.1996. “Managing the simultaneous execution of coupled phases in concurrent
product development”. IEEE Transactions on Engineering Management, 43(2),
210- 217
Krishnan V, Eppinger SD and Whitney DE.1997. “A model based framework to overlap
product development activities”. Management Science, 43(4), 437-451.
Langerak F, Peelen E and Nijssen E.1999. “A laddering approach to the use of methods
and techniques to reduce the cycle time of the new to the firm products”. J ournal of
Product Innovation Management, 16, 173-182.
Larson EW and Gobeli DH.1989. “Significance of project management structure on
development success”. IEEE Transactions on Engineering Management, 36(2),
119-125.
Laufer A, Denker GR, and Shenhar AJ.1996. “Simultaneous management: the key to
excellence in capital projects”. International J ournal of Project Management, 14(4),
189-199.
Liker JK, Collins PD, and Hull FM.1999. “Flexibility and standardisation: Test of a
contingency model of product design-manufacturing integration”. Journal of Product
Innovation Management, 16, 248-267.
Loch HL and Terwiesch C .1999. “Accelerating the process of engineering change orders:
Capacity and congestion effects”. Journal of Product Innovation Management, 16,
145-159.
McDermott CM.1999. “Managing radical product development in large manufacturing
firms: a longitudinal study”. J ournal of Operations Management, 17, 631-644.
Meyer MH, Tertzakian O and Utterback JM.1997. “Metrics for managing research and
development in the context of the product family”. Management Science, 43(1), 38-
111,
Milson MR, Raj RP and Wilemon D.1992. “A survey of major approaches for accelerating
new product development”. Journal of Product Innovation Management, 9, 53-69.
Moder JJ, Philips CR and Davis EW.1983. “Project management with CPM, PERT and
precedence diagramming”. Van Nostrand Reinhold, New Y ork.
Murmann PA.1994. “Expected development time reductions in the German mechanical
engineering industry”. J ournal of Product Innovation Management, 11, 236-252.
Notzon 1.2000. “Effective design of phase overlapped product development processes- a
system dynamics based analysis”. Unpublished Mphil thesis, University of Bergen.
Olson EM, Walker OC and Reukert RW.1995. “Effective new product development: the
moderating role of product innovativeness” Journal of Marketing, 59, 48-62..
Page AL.1993. “Assessing new product development practices and performance:
establishing crucial norms”. J ournal of Product Innovation Management, 10, 273-
290.
Pinto JK, and Covin JG.1989. “Critical factors in project implementation: A comparison of
construction and R&D projects”. Technovation, 9, 49-62.
Richardson GP and Pugh III AL .1981. “Introduction to system dynamics with DYNAMO”.
The MIT press, Cambridge, MA
Rodriguez AG and Bowers J.1996. “System dynamics in project management: a
comparative analysis with traditional methods”. System Dynamics Review 12(2),
121-139.
Shenhar AJ.1998. “From theory to practice: towards a typology of project management
styles”. IEEE Transactions on Engineering Management, 45(1), 33-48.
Smith PG and Reinertsen DG.1991. “Developing products in half the time”. Van Nostrand
Reinhold, New Y ork.
Souder WE and Moenaert RK.1992. “Integrating marketing and R&D project personnel
within innovation projects: An information uncertainty model”. Journal of Management
Studies, 29, 485-512.
Souder WE, Sherman JD, and Davis-Cooper R.1998. “Environmental uncertainty,
organisational integration, and new product development effectiveness: a test of
contingency theory” Journal of Product Innovation Management, 15, 520-533.
Sterman JD.1992. “System dynamics modeling for project management’. Unpublished
working paper, System dynamics group, Sloan School of Management, Massachusetts
Institute of Technology, Cambridge, MA.
Sterman JD.1994.” Learning in and about complex systems”. System Dynamics Review
10(2-3), 291-330.
Sterman JD.2000. “Business dynamics. Systems thinking and modeling for a complex
world”. Mc-Graw Hill/Irwine, Intemational edition.
Steward DV.1981. “The design structure system: a method for manging the design of
complex systems”. IEEE Transactions in Engineering Management, EM-28,3 ,71-74.
Swink ML.1998. “A tutorial on implementing concurrent engineering in new product
development”. Journal of Operations Management, 16, 103-116.
Swink ML.1999. “Threat to new product manufacturability and the effects of development
team integration processes”. J ournal of Operations Management, 17, 691-709.
Swink ML.2000. “Technological innovativeness as a moderator of new product
development design integration and top management support”. Journal of Product
Innovation Management, 17, 208-220.
Swink ML, Sandvig CJ and Pearson AW.1996. “Customizing concurrent engineering: Five
case studies”. J ournal of Product Innovation Management, 13(3), 229-244.
Takeuchi H and Nonaka! .1986. “The new new product development game”. Harvard
Business Review, January-February, 137-146.
Tatikonda MV.1999. “An empirical study of platform and derivative product development
projects”. Journal of Product Innovation Management, 16, 3-26.
Tatikonda MV and Rosenthal SR.2000a. “Technology novelty, project complexity, and
product development project execution success: A deeper look at task uncertainty in
product innovation”. IEEE Transactions on Engineering Management, 47(1), 74-
87.
Tatikonda MV and Rosenthal SR.2000b. “Succesful execution of product development
projects: Balancing firmness and flexibility in the innovation process”. J ournal of
Operation Management, 18, 401-425.
Tatikonda MV and Montoya-Weiss MM.2001. “Integrating operations and marketing
perspectives of product innovation: The influence of organizational process factors and
capabilities on development performance”. Management Science, 47(1), 151-172.
Thomke S and Fujimoto T.2000. “The effect of “Front-loading” problem solving on
product development performance”. Journal of Product Innovation Management, 17,
128-142.
Trygg L.1993. “Concurrent engineering practices in selected Swedish companies: a
movement or an activity of the few?”. Journal of Product Innovation Management,
10(5), 403-415.
Tumer JR and Cochrane RA.1993. “Goals and methods matrix: coping with projects with
ill defined goals and/or methods for achieving them”. International J ournal of Project
Management 11 (2), 93-102.
Ulrich TK.1995. “The role of product architecture in the manufacturing firm”. Research
Policy 24, 689-710.
Ulrich TK and Eppinger SD.1999. “Product design and development”. Mc-Graw
Hill/Irwine, International edition.
Wheelwright SC and Clark KB.1992. “Revolutionizing product development: Quantum
leaps in speed, efficiency and quality”. The Free Press, New Y ork.
Williams TM.1997. “The need for new paradigms for complex projects”. In Williams TM
(Eds) “Managing and Modelling Complex Projects”. Kluwer Academic Publishers.
Williams TM.1999a. “The need for new paradigms for complex projects”. International
Journal of Project Management 17(5), 269-273.
Williams TM.1999b. “Seeking optimum project duration extension”, Journal of the
Operational Research Society, 50, 460-467.
Wind J and Mahajan V.1997. “Issues and opportunities in new product development: an
introduction to the special issue”. J ournal of Marketing Research 34(1), 1-12.
Zirger BJ and Hartley JL .1994. “A conceptual model of product development cycle time”.
Journal of Engineering and Technology Management, 11, 229-251.
Zirger BJ and Hartley JL.1996. “The effect of acceleration techniques on product
development time”. IEEE Transactions on Engineering Management, 43(2), 143-152.