Butterfield, Tristan with Michael Yearworth  "The distribution of project performance: initial investigations of its nature and what we can learn from it", 2014 July 20-2014 July 24

Online content

Fullscreen
The distribution of project performance: initial investigations of
its nature and what we can learn from it

Tristan Butterfield”, Dr Mike Yearworth!

‘Systems Centre, Faculty of Engineering, University of Bristol, Bristol, UK

Thales Research and Technology, Thales UK, Reading, UK

tristan.| field@pbristol.ac.uk, mike.yearworth@bristol.ac.uk

Abstract— All too ofien projects perform very differently to how they are expected to, and
indeed, how organisations would wish them to. There have been many attempts to further our
understanding of the reasons for this behaviour by looking at the dynamics that exist within a
single project environment. This paper looks to investigate the nature of the distribution of
the performance of a number of projects, across a portfolio, and poses the question of
whether unexpected project performance should in fact be expected. The aim of this work is
to provide an initial framework to explore this question by investigating the distribution of
simulated results from a System Dynamics project model based on the rework loop.
Furthermore this research gives an opportunity to further investigate the hypothesis that this
distribution may follow a power law, as has been discussed in literature and also within our
own research team.

Keywords—Project Performance; Portfolio; Rework; Power Law; System Dynamics.

1 INTRODUCTION

This paper details the authors’ investigations into the nature of how project performance
might be distributed across a portfolio of projects within an organisation. The purpose of
conducting this work was to try and illuminate the issue of whether it is reasonable to expect
that it is possible to reduce the variance of actual project performance against what is
estimated and also how one might go about achieving this.

This has been carried out by running simulations using a System Dynamics project model
and contrasting against basic estimates for the performance of these simulated projects using

parameters devised from an analogy to past experience. From this the ‘magnitude’ of project
actual per formance

estimated per formance
distributed across many projects. The hypothesis we propose, in line with the work of
Budzier & Flyvbjerg (2011), is that this distribution should, at least partially, follow a power
law. This is a distribution of the form: P(X > x) = Cx~*.

performance (i.e. ) can be calculated and plotted to show how this is

The testing of this hypothesis, through the failure to falsify, could be seen to indicate that the
poorly performing projects often regarded as ‘outliers’ or ‘one-offs’ are indeed of the same
nature as other projects and should hence not be considered as different.

2 BACKGROUND

This section explores the background and reasons for this research, the validity of the System
Dynamics model used and also the concept of power laws in the context of project
performance.

2.1 Research Agenda
This piece of research has evolved from the wider research agenda of trying to address the
issue of improving the estimation of complex project performance within Thales UK by the
use of parametric models. This wider research agenda has already yielded a System
Dynamics project model based on the rework loop (Walworth et al. 2013).

In the ongoing effort to calibrate this model for use with actual projects in Thales UK many
questions have emerged regarding the issues surrounding the estimation and improvement of
project performance. One of these strands of question has been the notion of what the
distribution of project performance should look like across a portfolio of projects within an
organisation. Or in other words, how much variance from estimations of future performance
should one really expect?

Hence, with these thoughts and recent developments in literature (Budzier & Flyvbjerg 2011;
Budzier & Flyvbjerg 2013) the research reported here was devised in order to investigate
what the existing System Dynamics project model, which has been shown to produce valid
behaviour (Walworth et al. 2013), predicts for this distribution.
2.2 Theoretical Background of the Rework Loop Model

The System Dynamics project model used, shown in Figure 1, is an extension of the model
under development at Thales UK and already presented by Walworth et al (2013). The
rework loop models work flowing through a project and explicitly acknowledges that a
portion of this work is done incorrectly and will need correcting (i.e. reworking). The desired
use of this model is the creation of planned lines (i.e. estimates) for projects against which
collected metrics can be reviewed to give an indication of performance. Of course in this
application the model is being used to generate the ‘real’ performance of randomly generated
project simulations.

The model used here was, first shown by Cooper & Mullen (1993), has been well
documented. There is an established acceptance of the rework loop as the base of a System
Dynamics project model (Lyneis & Ford 2007) and there are numerous examples of this
structure in use (Cooper & Lee 2009; Ford et al. 2007; Ford & Sterman 1998; Lyneis et al.
2001; Reichelt & Lyneis 1999). Indeed there have been claims that the rework loop is the
“canonical structure” (Lyneis & Ford 2007, p.159) for System Dynamics project models.

The outputs from the model, as illustrated in Figure 2, are not calibrated but have already
been shown (Walworth et al. 2013) to be of the nature of what has been shown to be expected
in literature (e.g. Mawby & Stupples 2002; Putnam 1978) and also what has been observed
from Thales UK data.

Number of

people Number of ;
Quality Requirements Quality
Factor Lookup
Resource Work Really
Done
a
Gs q |, Work Done
Work to be Done Rate Right Rate
Done = Quality of
Work Done
Reschedule Work Done
Rate Wrong Rate
i
Known “ Undiscovered
Rework Rework
Rework
Discovery
<Time>__ ew Rate
ae.
Urgency
Attention
Span
Figure 1 — System Dynamics Project Model
1500
1250 ———
E 1000
8 re
§ 750
E a7
2
% 500
g rs
*
250 :
0
0 12 24 36 48 60

Month

Figure 2 — Example Output from Model (Requirements Completed against Time — assuming
constant level of effort applied)


2.3 The Distribution of Project Performance & Power Laws

Budzier & Flyvbjerg have shown that the distribution of ICT project performance is “far
from normally distributed” (2013, p.14) and can be fitted to a power law distribution. They
reject the notion that poorly performing ‘outlier’ projects come from a different probability
regime to other projects and hence conclude that they must be considered in the same frame
of reference. They go on to conclude that these outlier projects are not fundamentally any
different to other ‘normal’ projects and hence should not be dismissed as one-off events. This
is an important point for improving industrial practice, where too often these poorly
performing project outliers are dismissed as such (March & Shapira 1987). Budzier &
Flyvbjerg also argue that this can be attributed to “Black Swan Blindness” (2011, p.13) in
addition to the bias towards optimism for project performance previously reported (Flyvbjerg
2008; Jorgensen & Grimstad 2005). A “Black Swan” is a rare, high impact event (Taleb
2005; Taleb 2007) and so in terms of a project would be a very poorly performing project,
probably considered outside of the normal bounds of performance, that would have
potentially ruinous impacts for the project organisation.

Whilst this background work is concerned with the ICT sector the authors of this paper
believe that this is an analogous scenario to the Systems Engineering sector where they are
conducting their research. Furthermore they believe that this is novel research in a relatively
sparse topic that has the potential to have significant insight into the problem of addressing
poor problem performance.

A power law is a probability distribution that follows the identity (Mitzenmacher 2004):
P(X >x)=Cx“%

Where P(X > x) is the probability that a random variable X is greater than the given variable
x, a is the exponent of the equation and C is a constant. In the case of investigating the
distribution of project performance P(X > x) would refer to the probability that any random
actual performance

———_————__) than the
estimated performance

specific magnitude in question. Hence, for example, P(X > 1.0) could be calculated giving
the probability of any project performing worse than the estimate.

project would have a greater magnitude of performance (

Power law behaviour has been shown to be present in many different environments (Newman
2005; Clauset et al. 2009; Mitzenmacher 2004) and their presence can be identified via the
creation of histograms of given data using logarithmic binning (Newman 2005). The presence
of a governing power law can then be easily identified by a straight trend line when this
histogram is plotted on logarithmic scales, as can be seen in the examples of the population of
cities or the magnitude of earthquakes (Newman 2005).

3 METHOD

In order to investigate how project performance might be distributed the existing System
Dynamics model, as detailed in Section 2.1, was used to generate data for simulated project
performance across a randomised portfolio of projects. These simulations were taken as the

‘actual’ performance of the project and then compared against performance estimates for the

actual performance

project. Hence the magnitude ( ) of the each project’s performance was

estimated performance
calculated and the distribution of this was plotted.
3.1 Model Setup and Assumptions

The Vensim® software package was used for modelling and simulation. The model was set
up to run from time 0-240 (months) in time steps of 0.0625 using integration type RK4

Auto.
As part of this process the following assumptions were made:

¢ The System Dynamics model used produces valid behaviour based on the inputs
despite not producing calibrated numerical outputs.

¢ The estimation method described in Section 3.4 is analogous to general practice,
namely using past experience to predict future performance.

¢ The distribution of project performance produced with this method would be of the
same nature, although skewed, to that of one produced using a calibrated model and
estimation method.

3.2. Randomised Parameterisation of Simulations
There are 7 input parameters for the System Dynamics model, for each simulation 4 of these

input parameters were randomly generated (within Microsoft Excel) according to the
following rules:

¢ Number of Requirements: Uniformly distributed between 100 and 5,000 in intervals
of 50. This parameter is simply the size of the project.

¢ Number of People: Uniformly distributed between 2 and 50. This parameter equates
to the number of full-time project staff available to work on the project.

* Quality Factor: Normally distributed with a mean of 5.5 and standard deviation of 1
within a permitted range of 1-10. This parameter takes into account the relative
suitability of the project team for the project.

* Quality of Work Done: Normally distributed with a mean of 0.75 and standard
deviation of 0.05 within a permitted range of 0.51.0. This parameter is the fraction
of work done correctly (i.e. 1 — rework fraction). For example if the Quality of Work
Done = 0.8 then 80% work being done is done correctly and 20% will require rework.
It should be noted that this fraction applies to all work, including requirements that
have already been reworked.

For both the Quality Factor and the Quality of Work Done parameters any randomly
generated values which fell outside the permitted range were manually rationalised to the
upper or lower bound of the input range as appropriate.

The input parameters for Intensity, Urgency and Attention Span (which combined determine
the rate at which rework is discovered) were all set to their default values for each of the
simulation runs. These parameters are a direct analogy to the Jelinski-Moranda equation for
defect discovery in software (Jelinski & Moranda 1972).

3.3 Simulation & Processing
Vensi was used to System Dynamics model using the randomised parameters
and was set up to export the simulation data which were then processed and collated
manually. The following results were captured for each simulation run: the project time to
complete; the number of requirements actually completed; and the number of requirements
‘considered’ to have been completed (i.e. requirements actually completed + the level of
undiscovered rework).

Each project was subject to the following stopping rule: the project was deemed to have
finished when the change in the number of requirements ‘considered’ to be done fell below 1
for a single month. This was except in the cases where the A requirements ‘considered’ done
falls below | early on in the lifecycle due to a large amount of rework being discovered. This
was considered normal and not taken as the stopping point for the project.

For some simulation runs the total number of requirements actually done or ‘considered’
done exceeded the total number of requirements for the project due to integration and
rounding errors. In these cases these numbers were rationalised to the total number of
requirements.

3.4 ‘Estimation’
In addition to the generation of the simulated ‘real’ project performance an estimated

performance was also needed for each of the simulation runs in order to calculate the project
performance magnitude.

Estimates were created for each of the simulation runs based on the results of a smaller sub-
set of 10 simulations. From these a figure for the average number of requirements / staff
member / month was calculated. This figure was based on the number of requirements
‘considered’ done and subject to the same stopping rule as described in section 3.4.

This figure was then applied to each of the simulation runs in order to calculate an estimate
for the project duration. The simulated ‘real’ results were then compared against the estimate

. . actual performance
and hence the magnitude of the project performance ( _tenlalnen formance — ) was calculated.
estimated performance

4 RESULTS

Figure 3 gives the estimated values for P(X > x), meaning the probability that the magnitude
of a random project X will be larger than the magnitude of a given project x. For example
when x = 1.0 (performed exactly as expected) P(X = x) ~ 60% (i.e. there is a 60% chance
that any project will perform worse than expectations).

Figure 4 shows the log-log graph of the data presented in Figure 3. If the distribution of
project performance was governed by a power-law (or at least a section of the distribution)
we would expect to see a straight line in this graph. Although far from conclusive one could
make the argument for a straight trend line for the data between the log magnitude of 0.00
and 0.60. This corresponds to the data for runs where the magnitude was between | and 4
(approximately 75% of the runs).

We can also extract the following raw statistics for the magnitude of performance from the
simulations:

¢ Median = 1.19

¢ Mean = 1.26

¢ Standard deviation = 0.79

¢ Minimum = 0.15

¢ Maximum = 6.42

Whilst it is hard to draw any real conclusions from these statistics it is very noticeable that
the range for simulated project performance is very large. The projects performing much
better than estimates particularly stand-out due to the scarcity of analogous examples in the
real world.

A further point to draw from this is in comparison to a previous iteration of these simulations,
which applied a uniform distribution to both the Quality of Work Done & Quality of Staff
rather than a normal distribution. This change has pulled the statistics into a much more
believable territory — previously the average magnitude was considerably higher and there
was also little evidence to suggest the presence of a power-law governing the distribution.

Estimated P(X2x)

100.00%

Initial Results - Estimated P(X2x) Against Magnitude

90.00%

Vad

80.00%

70.00%

60.00%

50.00%

40.00%

30.00%

20.00%

rai
ya

10.00%

0.00%

0.00

1.00 2.00 3.00 4.00 5.00
i of (Actual /

6.00

7.00


Initial Results - Log Estimated P(X2x) Against Log Magnitude

-0.80 -0.60 -0.40 -0.20 0.00 0.20 0.40 0.60 0.80 1.00

0.00
—
—~
0.50
*\

Al
1.008

a

z \

s

=

iG
1.50;

3 ba
2.00 \

\
2 Log i of Per (Actual / Esti )
Figure 4


5 DISCUSSION

From the interim results presented in Section 4, a result of 200 simulations, it appears that the
assertion that this distribution is at least partially governed by a power law cannot be
dismissed as this stage and it appears that it may be correct. Further work in analysing a
larger sample of the order of 10,000 simulations will lead to a clearer conclusions for this
point.

If this were to be proved the case then it could be said that the System Dynamics model is a
power law generating model and, as we believe that the behaviour generated by the model is
valid, that we would expect to see analogous behaviour in the real world data. Hence we
believe that this work provides a suitable framework to further investigate the claims of
Budzier & Flyvbjerg (Budzier & Flyvbjerg 2011; Budzier & Flyvbjerg 2013) in a Systems
Engineering environment and also as a comparison against real project data from
organisations.

The impact for industry of these conclusions is not, perhaps, immediately evident. However
the sheer awareness that the poorly performing projects, which are so often treated as outliers
or one-offs, are in fact of the same nature as ‘normal’ projects is an important step in itself.
With this awareness it might be possible to reduce the “Black Swan Blindness” (Budzier &
Flyvbjerg 2011, p.13) of an organisation and perhaps reduce the impacts of any optimism
bias that may be present. This could lead to an organisation with a much more insightful view
of future performance.

One explanation for this behaviour could be that, although all parameters of the model can be
seen explicitly in this example, some of the inputs that drive this behaviour are intangible and
unmeasurable. Furthermore, estimates, in both this work and also in reality, are generated
based on known quantities and past experience without taking these hidden values into
account.

It is proposed that it is a combination of these hidden parameters (Quality Factor, Quality of
Work Done & Rework Discovery Rate), particularly with a large project, can lead to a
tipping point that causes the project to perform particularly badly against expectations and
hence classification as an outlier of ‘black swan’. One practical proposal from this finding is
the recommendation for making these hidden parameters more visible, or at least explicitly
acknowledging their hidden nature when making estimations. It is also proposed that an
extension of this work could be an investigation into these tipping points within the model
with the approach discussed by Gross & Feudel (2006).

If we consider addressing the issue of poor project performance as a complex problem, or
indeed as a wicked problem (Rittel & Webber 1973), and that we are most likely operating in
an environment where there are divergent views of what the problems are and how they
should be tackled (i.e. we are operating in a Complex-Pluralist environment (Jackson 2003))
then a Problem Structuring Method (PSM) approach may be appropriate (Rosenhead 1996;
Mingers & Rosenhead 2004; Yearworth & White 2014).

It is proposed that the value of the framework that this work sets out, for investigating the
distribution of project performance, might best be realised by incorporating it into a PSM
approach which would enable greater understanding of the system where there is not
necessarily a consensus about the problem or the solution (Rosenhead 1996) or indeed where
the problem may not be solvable (Yearworth et al. 2013) if it is wicked.

Further work is proposed as to how the framework proposed and inherent modelling could be
included in a PSM approach that would be suitable and palatable for a project based

organisation, such as Thales UK.

Of course there are a number of limitations to this work and these include the fact that the
current model used is based on a single-stage rework loop. This is in contrast to how most
projects would be made up of multiple rework loops corresponding to different stages of
project development. This abstraction may change the dynamics of the proposed tipping
points and stability within the system.

Also, the research does not consider or take into account size of the project — i.e. a small
project vastly over budget may not be of great risk to a company but a very large project
twice over budget could be potentially ruinous.

Furthermore, if comparing against real project data then values for actual performance and
estimated performance will most likely be in the form of financial data. Whilst this is
comparable it is not identical to the technical performance discussed in this paper. In order to
compare against data from an organisation the System Dynamics model would have to be
calibrated and parameterised sufficiently if there was a desire to extract numerical outputs
from the distribution (i.e. probabilities) rather than simply a comparison of the nature of the
distribution. The task of acquiring suitable data to calibrate the model is non-trivial.

6 CONCLUSIONS

This section provides some brief conclusions based on the interim results from the System
Dynamics project model and will be refined following further work.

It appears that this distribution may be governed by a power law, and at the least this
hypothesis has not been falsified.

Very poorly performing projects can be explained in the same probability regime as ‘normal’
projects and should not be dismissed as one-offs and not considered when planning for the
future.

ACKNOWLEDGMENTS

The authors would like to thank their fellow members of the ‘metrics’ research team at the
University of Bristol and at Thales UK. We would especially like to thank Thomas Walworth
for his work in developing the System Dynamics model and also Hillary Sillitto for his
contribution to the discussion about the relevance of power laws in this environment. Tristan
Butterfield is registered on the Engineering Doctorate (EngD) in Systems programme at the
University of Bristol. This research is supported by the EPSRC funded Industrial Doctorate
Centre in Systems (Grant EP/G037353/1) at the University of Bristol and by Thales UK.

REFERENCES

Budzier, A. & Flyvbjerg, B., 2011. Double Whammy — How ICT Projects are Fooled by
Randomness and Screwed by Political Intent. Available at:
http://www.ssrn.com/abstract=2238057 [Accessed January 14, 2014].

Budzier, A. & Flyvbjerg, B., 2013. Making-Sense of the Impact and Importance of Outliers
in Project Management through the Use of Power Laws. In Proceedings of IRNOP
(International Research Network on Organizing by Projects), At Oslo. pp. 1-28.

Clauset, A., Shalizi, C.R. & Newman, M.E.J., 2009. Power-Law Distributions in Empirical
Data*. SIAM Review, 51(4), pp.661—703.

Cooper, K. & Lee, G., 2009. Managing the Dynamics of Projects and Changes at Fluor. In
Proceedings of the International System Dynamics Conference. Albuquerque, pp. 1-27.

Cooper, K.G. & Mullen, T.W., 1993. Swords & Plowshares - The Rework Cycles of Defense
and Commercial Software. American Programmer, 6.

Flyvbjerg, B., 2008. Curbing Optimism Bias and Strategic Misrepresentation in Planning :
Reference Class Forecasting in Practice. European Planning Studies, 16(1), pp.3-21.

Ford, D.N., Lyneis, J.M. & Taylor, T.R.B., 2007. Project controls to minimize cost and
schedule overruns: a model, research agenda, and initial results. In 2007 International
System Dynamics Conference. pp. 1-27.

Ford, D.N. & Sterman, J.D., 1998. Dynamic modeling of product development processes.
System Dynamics Review, 14(1), pp.3 1-68.

Gross, T. & Feudel, U., 2006. Generalized models as a universal approach to the analysis of
nonlinear dynamical systems. Physical Review E, 73(1), p.016205. Available at:
http://link.aps.org/doi/10.1103/PhysRevE.73.016205 [Accessed March 10, 2014].

Jackson, M.C., 2003. Systems Thinking: Creative Holism for Managers, Chichester: John
Wiley & Sons.

Jelinski, Z. & Moranda, P.B., 1972. Software reliability reseach. In W. Freiburger, ed.
Statistical Computer Performance Evaluation. Academic Press, pp. 465-484.

Jorgensen, M. & Grimstad, S., 2005. Over-optimism in Software Development Projects: “The
winner’s curse.” In Proceedings of the 15th International Conference on Electronics,
Ce ications and Comp ‘s (CONIELECOMP 2005). pp. 280-285.

Lyneis, J.M., Cooper, K.G. & Els, $.A., 2001. Strategic management of complex projects: a
case study using system dynamics. System Dynamics Review, 17(3), pp.237-260.
Available at: http://doi.wiley.com/10.1002/sdr.213 [Accessed March 15, 2013].

Lyneis, J.M. & Ford, D.N., 2007. System dynamics applied to project management : a survey
, assessment , and directions for future research. System Dynamics Review, 23(2),
pp.157-189.

March, J.G. & Shapira, Z., 1987. Managerial Perspectives on Risk and Risk Taking.
Management Science, 33(11), pp.1404-1418.

Mawby, D. & Stupples, D., 2002. Systems Thinking for Managing Projects. In Engineering
Management Conference, 2002. IEMC’02. 2002 IEEE International. EEE, pp. 344—
349,

Mingers, J. & Rosenhead, J., 2004. Problem structuring methods in action. European Journal
of Operational Research, 152, pp.530-554. Available at:
http://linkinghub.elsevier.com/retrieve/pii/S037722 1703000560 [Accessed October 18,
2013].

Mitzenmacher, M., 2004. A Brief History of Generative Models for Power Law and
Lognormal Distributions. Jnternet Mathematics, 1(2), pp.226-251. Available at:
http://www.tandfonline.com/doi/abs/10.1080/15427951.2004.10129088 [Accessed
January 14, 2014].

Newman, M.E.J., 2005. Power laws, Pareto distributions and Zipf’s law. Contemporary
Physics, 46(5), pp.323-351. Available at:
http://www.tandfonline.com/doi/abs/10.1080/00107510500052444 [Accessed January
27, 2014].

Putnam, L.H., 1978. A General Empirical Solution to the Macro Software Sizing and
Estimating Problem. JEEE Transactions on Software Engineering, SE-4(4), pp.345-361.
Available at: http://ieeexplore.ieee.org/Ipdocs/epic03/wrapper.htm?arnumber=1702544.

Reichelt, K. & Lyneis, J.M., 1999. The dynamics of project performance: benchmarking the
drivers of cost and schedule overrun. European Management Journal, 17(2), pp.135—
150.

Rittel, H.W.J. & Webber, M.M., 1973. Dilemmas in a General Theory of Planning*. Policy
Sciences, 4, pp.155—169.

Rosenhead, J., 1996. What’s the Problem? An Introduction to Problem Structuring Methods.
Interfaces, 26(6), pp.117-131.

Taleb, N.N., 2007. Black Swans and the Domains of Statistics. The American Statistician,
61(3), pp.198-200. Available at:
http://www.tandfonline.com/doi/abs/10.1198/0003 13007X219996 [Accessed March 3,
2014].

Taleb, N.N., 2005. The Roots of Unfairness: the Black Swan in Arts and Literature. Literary
Research/Recherche Litteraire, 21, pp.241-254.

Walworth, T. et al., 2013. Early estimation of project performance : the application of a
system dynamics rework model. In JEEE International Systems Conference.

Yearworth, M. et al., 2013. Integrating Problem Solving and Research Methods Teaching for
Systems Practice in Engineering. Procedia Computer Science, 16, pp.1072—1081.
Available at: http://linkinghub.elsevier.com/retrieve/pii/S 1877050913001 142 [Accessed
October 13, 2013].

Yearworth, M. & White, L., 2014. The Non-Codified Use of Problem Structuring Methods
and the Need for a Generic Constitutive Definition. European Journal of Operational
Research. Available at: http://linkinghub.elsevier.com/retrieve/pii/S037722 1714001301
[Accessed February 21, 2014].

Metadata

Resource Type:
Document
Description:
All too often projects perform very differently to how they are expected to, and indeed, how organisations would wish them to. There have been many attempts to further our understanding of the reasons for this behaviour by looking at the dynamics that exist within a single project environment. This paper looks to investigate the nature of the distribution of the performance of a number of projects, across a portfolio, and poses the question of whether unexpected project performance should in fact be expected. The aim of this work is to provide an initial framework to explore this question by investigating the distribution of simulated results from a System Dynamics project model based on the rework loop. Furthermore this research gives an opportunity to further investigate the hypothesis that this distribution may follow a power law, as has been discussed in literature and also within our own research team.
Rights:
Date Uploaded:
March 16, 2026

Using these materials

Access:
The archives are open to the public and anyone is welcome to visit and view the collections.
Collection restrictions:
Access to this collection is unrestricted unless otherwide denoted.
Collection terms of access:
https://creativecommons.org/licenses/by/4.0/

Access options

Ask an Archivist

Ask a question or schedule an individualized meeting to discuss archival materials and potential research needs.

Schedule a Visit

Archival materials can be viewed in-person in our reading room. We recommend making an appointment to ensure materials are available when you arrive.