Lowry, Thomas with Sean McKenna, Teklu Hadgu and Elena Kalinina, "Using System Dynamics for Uncertainty Analysis and Integrated Risk Assessment in Geothermal Energy Development", 2012 July 22-2012 July 26

Online content

Fullscreen
USING SYSTEM DYNAMICS FOR UNCERTAINTY ANALYSIS AND INTEGRATED RISK.
ASSESSMENT IN GEOTHERMAL ENERGY DEVELOPMENT

Thomas S. Lowry, Elena Kalinina, Teklu Hadgu, Sean A. McKenna

Sandia National Laboratories
P.O. Box 5800 MS1137
Albuquerque, NM, 87059, USA
e-mail: tslowry@ sandia.gov

ABSTRACT

The objective of this study is to use system dynamics (SD) modeling to aid in the development and
management of geothermal energy production by placing uncertainties in knowledge and
understanding into a risk-based framework. Here, we focus on the development of the SD model, GT-
Mod, and its use in performing uncertainty analysis and integrated risk assessment. Built within the
Powersim development environment, GT-Mod simulates the economic and thermal performance of a
given geothermal energy site to calculate the levelized cost of electricity (LCOE) as a function of known
and unknown (i.e., uncertain) physical and economic conditions. GT-Mod uses a Monte-Carlo approach
to propagate uncertainties in a variety of economic and physical descriptor parameters to estimate the
integrated risk of achieving a target LCOE. Integrated risk assessment is an approach that focuses on the
uncertainties in knowledge and understanding that cause uncertainty in the predicted future and is
calculated as the sum of the consequence, C, multiplied by the range of the probability, AP, over all
estimations of a given exceedance probability, n, over time, t. GT-Mod can be used by engineers,
project planners, potential investors, etc. to identify the optimal solution space for a given set of site
characteristics, and power plant and well configurations. The tool identifies the key areas of uncertainty
that if better understood, would provide the largest gain in understanding and predictability and hence,
the largest reduction in risk. Furthermore, the tool is able to identify and assess the set of physical,
technological, and economic hurdles that are preventing a geothermal project from becoming market
competitive.

The analysis assumes a realistic but fictitious enhanced geothermal system (EGS) site with uncertainties
in the exploration success rate, the sub-surface thermal gradient, the reservoir permeability, and the
power plant performance. Economic uncertainties include uncertainty in the cost of exploration,
construction, O&M, and drilling. GT-Mod propagates input uncertainties by describing them with
probability density functions (PDF’s) and then simultaneously varying the PDF’s via a Latin Hypercube
Sampling (LHS) technique across multiple runs. Exceedance probabilities for the LCOE are then
calculated as a post-processing exercise. Results show that the LCOE assumes a lognormal distribution
with the tail skewed towards the higher values and a mean LCOE that is almost 25% higher than the best
estimate, which is based on the mean values of the input PDF’s. Correlation analysis indicates that
reductions in drilling costs and better characterization of the sub-surface environment will reduce risk
the most.

INTRODUCTION

Geothermal energy development requires assessment of the quality and accessibility of a resource, the
available materials, services, and technologies, the demand for power, and the economics of the entire
process. Each of these areas represents a complex system of systems that can be difficult to evaluate.
Adding to this difficulty is the fact that these systems are dependent on the behavior and states of the
other systems and sub-systems that comprise the whole. The full suite of systems and sub-systems
result in a set of multi-tiered dependency structures with multiple feedback loops that propagate
uncertainties in the inputs in non-linear and unintuitive ways. Understanding the propagation of these
uncertainties in the context of economic risk of development is paramount if geothermal energy
production is to become cost competitive.

This study uses an example enhanced geothermal system (EGS) and the uncertainties associated with
developing an EGS site to illustrate the approach. EGS is an approach for accessing thermal energy from
the earth that involves drilling deep (2-10km) boreholes into hot, geologic material (usually crystalline
rock) and extracting heat by first fracturing the rock, and then circulating a working fluid (usually water
or CO,) through the system. Estimates show that within the Continental United States alone, access to
only 2% of the heat from 3 to 10 km deep could meet 2,500 times the United States’ current total
energy use (MIT 2006). This type of potential is equally valid for most parts of the world. However,
while the potential of EGS is enormous, uncertainties in the cost of development, thermal performance,
and operational reliability have hindered its development. Complicating this situation is the fact that
these uncertainties are dependent variables, meaning that they can exist in dynamic relationship with
other processes and uncertainties.

This work is employing system dynamics in developing an integrated modeling tool called GT-Mod
(Lowry et al. 2010) that dynamically links the various connected yet disparate systems of a geothermal
problem to simulate the collective performance of the systems over time. Built within the Powersim
development environment, GT-Mod represents each of the individual systems of a geothermal energy
project as individual systems that communicate with each other using dynamic linkages of mass and/or
energy. The four primary systems in the model are the power plant, the geothermal reservoir, the
injection wells, and the production wells, with each of the primary systems composed of one or more
sub-systems. The conceptual structure of GT-Mod is shown in Figure 1.

Power Plant
Geofluid available energy

Net power production
Plant effluent

Production Wells Injection Wells
Headloss / Pressure change Headloss / Pressure change
PW effluent temperature IW effluent temperature
Production pumping requirements Injection pumping requirements

Geothermal Reservoir
Reservoir pressure drop

Production temperature
Thermal drawdown over time

Figure 1 - Conceptual layout of GT-Mod showing the four main systems and their primary sub-systems. Items in
red indicate calculations that are linked to systems or sub-systems outside its own.

GT-Mod simulates the time varying pressure regime, thermal drawdown, plant performance, and
economics as a single, system of systems. Economic analysis is accomplished through a real-time, two
way connection to a modified version of the Geothermal Energy Technology Evaluation Model (GETEM)
(Entingh et al. 2006) that calculates the levelized cost of electricity based on time-series performance
output from GT-Mod.
GT-Mod allows a user to define a probability distribution function (PDF) for any number of input
variables. The inputs can be defined using uniform, normal, log-normal, truncated normal, exponential,
or triangular distributions. GT-Mod uses a Monte Carlo approach to propagate the input uncertainties
by varying each of the PDF’s across its range of values via a Latin Hypercube Sampling (LHS) technique.
Output from the model is collected and processed to produce a cumulative probability function of the
LCOE (or any output metric) and to calculate the integrated risk as a function of the input uncertainty.

INTEGRATED RISK

Generally, uncertainty manifests in both the inputs and the outputs of an analysis. For the inputs,
uncertainty reflects the confidence that the value of an input is the ‘true’ value for the analysis in
question. Uncertainty in the outputs result from the propagation of input uncertainties, the
assumptions used to create the simulation algorithms, and numerical inaccuracies in the solution
method. The integrated risk assessment in GT-Mod is similar to that used by the insurance industry to
assess their exposure to loss and can be thought of as a means to quantify the influence of uncertainties
in the inputs on the range of outputs.

Integrated risk assessment relies knowing the consequence(s) of an event (or set of events) as well as
the probability of that event occurring. To quantify risk, we utilize the approach introduced by Helton
(Helton 1994) who defines risk as the sum of the consequence, C, multiplied by the range of the
probability, AP, over all estimations of a given exceedance probability, n, over time, t:

R= py) C(n, HAP(n) (1)

The risk calculated with equation (1) represents the sum of the risk for all events across all probabilities.
For our purposes, an ‘event’, or scenario, is the model output that results from a single combination of
input parameters. Integrated risk provides a metric to quantitatively compare different scenarios and to
assess the tradeoffs between lower-probability higher-reward scenarios versus higher-probability lower-
reward scenarios.

EXAMPLE PROBLEM

To illustrate the capabilities of GT-Mod, we use a fictitious EGS site that is configured to produce 30
MWe at the start of the simulation. Configuring the site is done automatically in GT-Mod and involves
setting the number of injection and production wells, the total mass flow rate of the working fluid
through the plant, well design parameters such as borehole diameters and casing lengths, and injection
and production pump depths and rates (if needed). The mass flow rate is kept constant throughout the
simulation, which means that electricity production drops over time as a consequence of the declining
production temperature and efficiencies. Example outputs showing the reduction in the production
temperature and power generation over time are shown in Figure 2.
230 35

225

AF
8
Power [MW]

Temperature [°C]
N N
=] B
uo Oo
B
uw

Temp [C] x | 10
200

Power [MW] \
195 ; 5

190 T T T T T 0
(0) 5 10 15 20 25 30
Time [yrs]
Figure 2 - Example output from GT-Mod showing the time variation in production temperature and power
production.

The uncertainty analysis focuses on the costs of drilling as well as the costs of raw material and labor.
Drilling costs are a function of the depth of the resource, the penetration rate of drilling, equipment
reliability, the cost of steel and cement, and the drill-rig labor rates. To introduce uncertainty in these
inputs, multipliers are used to vary the input about a default value. Other cost uncertainties are
introduced by adjusting the utilization factor (the percent of time the plant is operating), a multiplier on
the total plant cost, and the percent of indirect costs associated with building and operating the plant.
In all, eleven parameters are defined as uncertain and are listed in Table 1 below.

As the thermal gradient is varied, the resource depth is adjusted to match the 225 °C target resource
temperature. As mentioned above, the number of wells for each simulation is based on the 30 MWe
power output, and the brine effectiveness, which is calculated using a regression against the design
temperature. Variations in the mass flow rate, the number of fractures, and the fracture aperture
impact the hydraulic drawdown and thermal performance of the reservoir. In turn, the hydraulic
drawdown and depth of the resource influences whether or not pumping is needed and whether it is on
the injection side, the production side, or both. Within GT-Mod, the Gringarten (Gringarten et al. 1975)
analytical solution option was chosen to calculate the thermal drawdown and the Snow estimation
(Snow 1968) was chosen to calculate the pressure drop through the reservoir. All other sub-surface
parameters are kept constant, as are parameters describing the economics, operations, and
maintenance costs.
Table 1 - List of variable input parameters, their default values, and their distribution functions.

Distribution Distribution

Name Description Default Value
Type Parameters
Min: 85.0%
Utilization Factor % time plant is operating 95% Triangular Peak: 95.0%
Max: 98.0%
Adjusts turbine generator, $398.65 / kW,
Power Plant Cost condenser, $204.32 / kW, ,
Multiplier heat exchanger, and $50.21/kW, Uniform 0:80.20;
working fluid pump costs $36.32 / kW
% of plant cost to calculate Min es
Percent Indirect Costs Pore inclieet costs 8% Triangular Peak: 8.0%
Max: 12.5%
Casing Cost Multiplier Material costs of casing $2.01 /1b Uniform 0.80 — 1.20
Cement Cost Multiplier Material costs of cement $175.00/ ft Uniform 0.80 — 1.20
Fracture Aperture Effective fracture aperture imm Uniform 0.25 —3.00 mm
% water loss that must be Mins 2.0%
Subsurface Water Loss e water: Si sy must ee 5% Triangular Peak: 5.0%
Tee Max: 10.0%
Trouble Index Adjusts estimated driling and 10 Uniform 080-120
Multiplier casing time
reales Adjusts drilling penetration rate 2 Aas ioe Mi Uniform 0.80 - 1.20
Bit Life Multiplier Adjusts life of drilling bit 100 hrs Uniform 0.80 - 1.20
Thermal Gradient Adjusts thermal gradient 43.87 °C/km Normal we3e7 Chk
6 =9.9°C/km
RESULTS

The comparisons are made on the net revenue generated over the 30 year lifetime of the plant using the
following equation:

Reot — C = Rnet (2)
where R,o; [$] is the total revenue and C [S] is the total cost. The total revenue is calculated using:
SeP-TU = Reo 83)

where S, is the effective sale price of electricity [¢/kW-hr], P, is the production capacity of the power
plant, T is the lifetime of the power plant, and U is the utilization factor. The costs, C, for each scenario
are also calculated using equation (3) by substituting the calculated LCOE for the effective sale price, S..
The effective sales price of 9.829 ¢/kW-hr is based on data from the US Energy Information
Administration (US Energy Information Administration 2011) and was derived as a weighted average of
the monthly sales price of electricity from all sources for the residential, commercial, industrial, and
transportation sectors for 2009 and 2010. The net revenue for the default case, Dnet, is $166.0 million
dollars over 30 years (Dner assumes an LCOE of 8.5 ¢/kW-hr and a utilization factor of 95%).

Figure 3 shows the results for the LCOE as a cumulative distribution function (CDF) that describes the
probability that the LCOE will be below a given value. It is interesting to note that there is only a 32.1%
chance that the LCOE will be less than or equal to the default LCOE value of 8.5 ¢/kW-hr, despite the fact
that the default values for the variable inputs lie either at the center or the peak of their respective
PDF’s. While the default case is deemed the most probable from a parameter estimation point of view,

the distribution of the LCOE is not necessarily symmetrical about that value. In this case, the results are
skewed towards a higher LCOE than the default would indicate.

100%
90%
80%
70%
60%
50%
40%
30%
20%
10%

0%

Probability

95 105 115 125 135
LCOE [¢/kW-hr]

8.5

Figure 3 - Cumulative distribution function of the LCOE. The CDF shows the probability that the LCOE will be less
than a given value. The solid red line indicates the LCOE (8.5 ¢/kW-hr) and probability (32.1%) of the default
case.

Figure 4 shows a complimentary cumulative distribution (CCDF) plot of the net revenue, Rnet, as well as
the difference between Rner ANd Dyer. A CCDF plot describes the probability that the ‘real’ scenario will
be greater than the value at that probability. The plot shows that the probability of producing positive
revenue is about 89% (solid blue line). Conversely, the probability of exceeding the default performance
is only 31.2%, which means that if projections are based solely on the default input values, there is a 2
out of 3 chance that the actual performance will fall below that number.

100%

90%

=e

#

80%
70%

60% -
50% -+

@ Difference from Default

@ Net Revenue \ .
40% -

30% *

20%

10%

0% r T r 7 T

-§0.5 -$0.4 -$0.3 -$0.2 -$0.1 $0.0 $01
US Dollars

Probability

$0.4
Billions

$0.2 $0.3

Figure 4 - Complimentary CDF for net revenue and the difference between net revenue and the default case.
The solid red and blue lines indicate the probabilities associated with the ‘break even’ point of each distribution
(31.2% for net revenue, 89.0% for the difference).

The calculated risk for the difference between Rnet ANd Dnet is about $72.0 million (Figure 5). The risk is
calculated using equation (1) and assumes that the risk is zero for scenarios where Rye is greater than
Dnet and in this case, represents a loss as compared to the default scenario. The figure shows the
cumulative risk plotted over the Rnet - Dret CCDF, with the axes rotated so that probability is now on the
x-axis, and dollars are on the y-axis. The risk is not a probability function meaning that the final value of
$72.0 million is integrated across all revenues and all probabilities. The difference between Dre and the
risk is about $94.0 million, which now becomes the probabilistically weighted estimate of Rec and which
corresponds to an effective LCOE of 9.1 ¢/kW-hr. From a risk-based decision making point of view, the
decision maker must now decide if the potential gains are worth the risk.

Probability
0% 20% 40% 60% 80% 100%

90.20 f : : : :
2
5

$0.10 ia $71,944,544

oon oa
2
8
8-50.10
a
2 —— Dnet CCDF

-$0.20

— Risk \
-$0.30
-$0.40

Figure 5 - The CCDF for the difference in net revenue, Dye, and the integrated risk. The total risk for this
example is $71,944,544.

Correlation analysis is used to determine which inputs contribute the most to the variability in the LCOE
estimates (Table 2) and is useful for deciding on where to place future efforts to reduce uncertainty (i.e.,
risk) the most. In this case, changes in the trouble index, the penetration rate multiplier, and the
thermal gradient influence the value of the LCOE the most. Since the thermal gradient sets the depth of
the resource, it is clear that factors concerning the drilling time are important to the LCOE and if one
desires to reduce the LCOE, effort should be placed on reducing the drilling time. Conversely, if reducing
the drilling time is not feasible, reducing the uncertainty in the estimations of the drilling time will
provide more certainty to the LCOE predictions and reduce the risk of incorrectly assessing the site. The
next most influential inputs are the indirect costs followed by the casing material costs. It should be
noted that the correlations can be highly influenced by the PDF and more importantly, the spread of
potential values for each input and that when risk analysis of this type is used in the real world, care
should be given when forming the PDF’s.
Table 2 - Correlation coefficients for each of the variable inputs against the LCOE.

Variable Name Correlation with LCOE
Utilization Factor 0.011
Fracture Aperture -0.010

Subsurface Water Loss Percentage 0.001
PP Cost Adjustments -0.044
Indirect Cost Percentage -0.061
Trouble Index -0.192
Penetration Rate Multiplier 0.156

Bit Life Multiplier 0.007

Casing Cost Multiplier -0.052
Cement Cost Multiplier 0.039
Thermal Gradient -0.123

SUMMARY

Most of our understanding of a geothermal resource is obtained from indirect measurement and or
inference and even for cases where the knowledge is high, uncertainty remains. Models used to assess
the resource rely on this understanding to populate their inputs such that they reflect the effective
characteristics at the site. Due to model sensitivity, some inputs require high precision while others are
less stringent. Historically, when simulating thermal or economic performance, uncertainty has typically
been addressed by assuming a mean value for each of the inputs, and then perturbing the values about
that mean to try and bound the range of possible answers. That range is then reported as a mean
prediction plus or minus the variability about that mean.

In this study, we utilize system dynamics to link together the myriad of physical and economic systems
that comprise a geothermal energy assessment in order to address uncertainty. Called GT-Mod, the
model provides an integrated risk framework that aids decision and policy makers by providing a single
metric (integrated risk) to compare between scenarios. The approach propagates uncertainty in model
inputs using a Monte Carlo / Latin Hypercube Sampling approach to produce probabilistic output. The
example presented above is based on a consequence metric defined as the difference of the simulated
net revenue and a target value. The risk is calculated as the summation over all scenarios (i.e, over all
combinations of parameter inputs) of the product of the revenue deviation and its probability and
quantitatively describes the consequence of the gaps in knowledge and understanding of the site.
Integrated risk assessment provides a decision maker with a higher degree of insight regarding the
consequence of his or her decision while simultaneously identifying the areas where better
understanding would most help the decision making process.
REFERENCES

Entingh, D. J., G. L. Mines, G. Nix, A. Mansure, S. Bauer, S. Petty and B. Livesay (2006). DOE Geothermal
Electricity Technology Evaluation Model (GETEM): Volume I - Technical Reference Manual. Washington
DC, US Department of Energy, Office of Energy Efficiency and Renewable Energy.

Gringarten, A. C., P. A. Witherspoon and Y. Ohnishi (1975). "Theory of Heat Extraction from Fractured Hot Dry
Rock." Journal of Geophysical Research 80(8).

Helton, J., C. (1994). "Treatment of uncertainty in performance assessments for complex systems." Risk Analysis
14(4): 483-511.

Lowry, T. S., V. C. Tidwell, P. H. Kobos and D. A. Blankenship (2010). "A Multi-Tiered System Dynamics
Approach for Geothermal Systems Analysis and Evaluation." GRC Transactions 34: 85-90.

MIT (2006). The Future of Geothermal Energy: Impact of Enhanced Geothermal Systems (EGS) on the United
States in the 21st Century. An assessment by an MIT-led interdisciplinary panel., Massachusetts Institute
of Technology.

Snow, D. T. (1968). "Rock fracture spacings, openings, and porosities." Journal of the Soil Mechanics and
Foundations Division, Proceedings of American Society of Civil Engineers 94: 73-91.

US Energy Information Administration. (2011). "Electric Power Monthly Website." from
http://www.eia.doe.gov/cneaf/electricity/epm/epm_sum.html.

Metadata

Resource Type:
Document
Description:
We present a system dynamics model called ‘GT-Mod’ for assessing the development and management of geothermal energy production. The model simulates the entire geothermal energy cycle by representing the major components as a set of connected sub-systems that include the power plant, the injection well, the geologic reservoir, the production well, the surface feeder and distribution pipes, the pumps, and the economics. GT-Mod uses a Latin Hypercube Monte-Carlo approach to propagate uncertainties in various input parameters to calculate the systems’ thermal and power performance over the lifetime of the project and to assemble a probability distribution of the levelized cost of electricity (LCOE) that is used to estimate the integrated risk as a function of input uncertainty. Integrated risk is the summation of the product of consequence and probability over all probabilities and represents a comprehensive metric for benefit analysis that includes the full range of uncertainties in a particular problem. GT-Mod is also used to bound viable solution spaces and to identify areas of uncertainty that have the greatest influence on risk. An example based on a hypothetical but realistic geothermal site is presented that demonstrates the models application and highlights the suitability of the system dynamics approach.
Rights:
Date Uploaded:
January 1, 2020

Using these materials

Access:
The archives are open to the public and anyone is welcome to visit and view the collections.
Collection restrictions:
Access to this collection is unrestricted unless otherwide denoted.
Collection terms of access:
https://creativecommons.org/licenses/by/4.0/

Access options

Ask an Archivist

Ask a question or schedule an individualized meeting to discuss archival materials and potential research needs.

Schedule a Visit

Archival materials can be viewed in-person in our reading room. We recommend making an appointment to ensure materials are available when you arrive.