8 October, 1963
Walter M. Tisdale
President Evan R. Collins
PROGRESS REPORT NO. 15 °
1. Second floor of Dormitory No. 1 is being
poured along the west side.
2. large parking lot between Service Group
and Dormitory No. 1 is laid out, curbstones are being
poured and results continue to be successful. I believe
this will be repeated now without incident.
4, Columns for building "A" of the Service
Group are nearly all erected and we can expect comple-
tion on that portion shortly.
5. Six athletic fields are ready to be
seeded. This will probably occur late this week or
next,
Cc; Mr. Merle Hathaway
Dr. Ravid Hartley