Homer, Jack B. with Ivan Somers, "Defense Program Lifecycle Management: A Dynamic Model for Policy Analysis", 1988

Online content

Fullscreen
~160-

Defense Program Lifecycle Management:
A Dynamic Model for Policy Analysis

by
Jack B. Homer! and Ivan Somers2

1University of Southern California
2Hughes Aircraft Company
-l61-

Defense Program Lifecycle Management:
A Dynamic Model for Policy Analysis

ABSTRACT

The System Dynamics Lab at the University of Southern
California's (USC) has worked with Hughes Aircraft
Company's Electro-Optical and Data Systems Group to
develop a system dynamics model for analyzing alternative
policies available to a defense contractor for managing the
production program lifecycle. Program lifecycle
management is of prime importance to firms, like Hughes,
that design, manufacture, and maintain complex military
equipment. These firms have come under increasing
government scrutiny and control, Particularly with regard
to cost and schedule risks.

The USC-Hughes model addresses the notion that cost and
schedule risks can be substantially reduced through
improved program management, even in the face of
possible hurdles thrown up by customers and suppliers.
The model suggests, for example, that overruns,
particularly cost overruns, may be significantly’reduced--
without adversely affecting product quality--by carefully
limiting the number and type of discretionary mid-
production design improvements.

This presentation outlines the background and basic
structural elements of the USC-Hughes model,
demonstrates the model's ability to track historical data
from two different cases, and highlights some of the policy
findings that have emerged from the model.
-162-
Background

Client Motivation

¢ Project initiated in 1985 to analyze over-time impact of
design changes on cost and schedule risk.

¢ Concerns over cost amplified in an environment of
reduced Congressional budgets.

¢ Schedule slippages a chronic problem hurting customer
relations and jeopardizing contracts.

¢ Overruns recognized as a dynamic problem: result of
inefficiencies accumulating over entire program
lifecycle of engineering design, manufacturing, and
integrated logistics support (ILS).

Model Scope

¢ Model focuses on manufacturing and ILS phases of
lifecycle. In particular, what happens when design
imperfections are discovered mid-production?

¢ Significant design imperfections common in concurrent
production programs: Government often requires
manufacturing phase begin before design fully debugged
and tested.

¢ Model focuses on flows of parts, assembled units, and
engineering changes. Other factors (labor, equipment,
cash, etc.) assumed available and non-constraining.
~163-

Overview of Model Structure

Hughes/EDSG >
|eore
ngineeri
ECRs(3) ECRs(4
| -Design maturity et Customer
-Design changes

drawings
ECRs(2) 3S deviation/

waiver

requests
Manufacturing
deviations/
-Scheduling waivers
-Incorporation «
of changes l

-Part procurement

& fabrication part
-Unit assembly, ee
test & rework Vendors
<—____-_____—
parts
spare part units,
orders spare parts
ILS
-Field repair
& readiness

Sources of ECRs (Engineering Change Requests)
(1) Engineering analysis revealing design problems
(2) Test yield and producibility problems

(3) Field reliability problems

(4) New customer performance requirements
-164-

Case Studies and Policy Issues

Two Case Studies

¢ Model initially developed and calibrated to represent one
particularly troubled program still in production.

* Model "revalidation" involved recalibration to represent
a different production program already completed.

Central Policy Issues

¢ Mid-production engineering change requests (ECRs):
Most ECRs are internally generated rather than
customer-directed. Should such discretionary ECRs be
terminated altogether at some point during production?
Should each be accepted only if its expected impact
exceeds some minimum amount? Should they be
grouped together and released in blocks rather than in a
continuous stream?

¢ Disposition of old-version parts:
When new-version parts arrive to the factory, it is a
common practice to "purge" (discard) old-version parts
from raw inventory and work-in-process. Indeed, not to
do so may be considered a "deviation" from plans to roll
new-version parts into production quickly. Should this
practice of purging be modified? ,

¢ Ordering of parts:
Because of uncertainty in vendor delivery times, it is a
common practice to order parts so that most arrive well
before they are needed for assembly. This is known as
"front-loading" the parts delivery schedule. Should this
practice be modified?
Production Units

Production Units

-165-

CUMULATIVE SHIPMENTS, CASE 1

2500

2000 4

1500 ~

1000 4

Simulated

Historical

2.3 Month Avg. Delinquency

24 36 48 60 72 84 96

CUMULATIVE SHIPMENTS, CASE 2

2500

2000 +

1500 4

1000 4

500-7

Historical

24 36 48 60 72 84 96
Drawing Changes

Drawing Changes

~166-

CUM. ENGINEERING CHANGE REQUESTS, CASE 1

6000

5000 +

4000 4

Historical
Simulated
6.5 ECRs/Drawing on Avg.
Planned
T 7 T T
12 24 36 48 60 72 84 96
Month

3000

2500 4

2000 4

1500 4

1000

Historical c 4.3 ECRs/Drawing on Avg.

Planned

12 24 36 48 60 72 84 96
Constant Dollars

Constant Dollars

-167-

CUMULATIVE PROGRAM COSTS, CASE 1

4,00+8

3.0€+8 7

2.0e+8 4

1.0648

39% Overrun

Simulated

\

Planned

12 24 36 48 60 72 84 96

CUMULATIVE PROGRAM COSTS, CASE 2

2.0e+8

1.5e+8 5

1.0e+8 4

5.0e+7 5

18% Overrun

Simulated
\

Planned

-168-

Causal Structure Behind Problems
of Cost and Schedule

Customer
“we - OX.
Maturity Nw’ ON S ‘pesion
of Design * Changes
. |
a Purging of
Aacepiabilty ——_ 01¢-version
Parts
Unit Part Familiarity
Rework & Shortages with Parts
Repair
vA
+ Assembly Labor
Productivi
Parts “* ”
Ordered
| -
COST nell

i SCHEDULE
OVERRUN Retesting >> SLIPPAGE
-169~

Results and Recommendations

¢ Purging of old-version parts can generate severe parts
shortages largely responsible for cost and schedule
problems. It also disrupts assembly. Purging actually
slows the rate at which acceptable units are produced,
the opposite of its intended effect.

Should eliminate part purging, except where part
changes are customer-directed or "must-do" (i.e., non-
discretionary). Reach understanding with customers on
this policy so that use of old-version parts is not
generally considered a deviation.

* Marginal benefit of ECRs decreases as design improves,
but marginal cost remains the same. Also, marginal net
benefit is greater early during manufacturing phase,
before assembly comes up to speed. So, early
termination of discretionary ECRs can be significant
cost saver, also may reduce schedule slippage.

Filtering-out of less significant ECRs followed by
outright termination of all discretionary ECRs can cut
costs more than termination alone, but the additional
savings are relatively small, and appropriate
implementation is tricky. The benefits of filtering may
not be worth the extra effort and uncertainty involved.

Block release of mid-production design changes delays
their benefits and increases the disruption they cause.
They should be released without blocking.
-170-

Results and Recommendations (continued)

* Front-loading of the parts delivery schedule builds up
raw parts stocks and disguises the extra attrition caused
by unexpected rework and repair (plus any purging).
This can lead to the factory being caught short of parts
at end-of-contract should the production program be
temporarily or permanently discontinued. This may
result in much additional schedule slippage. Should
eliminate the practice of front-loading.

* When tested independently, "no part purging" and "ECR
termination" policies each led to major theoretical
reductions in cost and schedule overruns for the two
historical cases.

But "no part purging” had the greater impact, and
combination of the two policies led to relatively minor
additional cost improvement (and no additional schedule
improvement) over "no part purging" alone. Indeed, the
beneficial impacts of "ECR termination" taken alone are
largely due to its indirect elimination of much purging.

« Whether tested independently or together with other
policies, "no front-loading" policy led to sizeable
theoretical reductions in schedule slippage for the two
historical cases.

Metadata

Resource Type:
Document
Description:
The System Dynamics Lab at the University of Southern California’s (USC) has worked with Hughes Aircraft Company’s Electro-Optical and Data Systems Group to develop a system dynamics model for analyzing alternative policies available to a defense contractor for managing the production program life cycle. Program lifecycle management is of prime importance to firms, like Hughes, that design, manufacture and maintain complex military equipment. These firms have come under increasing government scrutiny and control, particularly with regard to cost and schedule risks.The USC-Hughes model addresses the notion that cost and schedule risks can be substantially reduced through improved program management, even in the face of possible hurdles thrown up by customers and suppliers. The model suggests, for example, that overruns, particularly cost overruns, may be significantly reduced--without adversely affecting product quality--by carefully limiting the number and type of discretionary mid-production design improvements.This presentation outlines the background and basic structural elements of the USC-Hughes model, demonstrates the model’s ability to track historical data from two different cases, and highlights some of the policy findings that have emerged from the model.
Rights:
Image for license or rights statement.
CC BY-NC-SA 4.0
Date Uploaded:
December 5, 2019

Using these materials

Access:
The archives are open to the public and anyone is welcome to visit and view the collections.
Collection restrictions:
Access to this collection is unrestricted unless otherwide denoted.
Collection terms of access:
https://creativecommons.org/licenses/by/4.0/

Access options

Ask an Archivist

Ask a question or schedule an individualized meeting to discuss archival materials and potential research needs.

Schedule a Visit

Archival materials can be viewed in-person in our reading room. We recommend making an appointment to ensure materials are available when you arrive.